Wilhelmshaven-Conneforde line put in operation

05.10.2020

With the Wilhelmshaven-Conneforde line, the Dutch-German transmission system operator (TSO) TenneT has commissioned an important grid expansion project for the German and European energy transition. The 380kV line from the new substation Fedderwarden near Wilhelmshaven on the German North Sea coast to the Conneforde substation in Ammerland, both in the federal state of Lower Saxony, is not only crucial for the transmission of mainly wind power and electricity from regional generators, but also for strengthening security of supply in northern Lower Saxony. Furthermore, it represents a novelty for the TSCNET shareholder in terms of technical implementation: “With this new line, we have put into operation the first pilot project with two underground cable sections in three-phase technology and connected it to the meshed power grid in Germany,” explained Tim Meyerjürgens, COO of TenneT.

The commissioning ceremony on 2 October 2020 in Fedderwarden was attended by representatives from politics, including Andreas Feicht, State Secretary at the German Federal Ministry for Economic Affairs, and Energy and Olaf Lies, Minister for the Environment, Energy, Construction, and Climate Protection of Lower Saxony. The new line is only about 30 kilometres long, but – together with the new construction of the Fedderwarden substation – “of great importance for the entire European electricity trade”, commented Olaf Lies. The Minister was impressed by TenneT’s latest milestone in the energy transition. State Secretary Feicht referred to the newly gained potential for integrating large amounts of wind power into the German electricity market and the technical relevance of the pilot project: “Knowledge obtained in such pilot projects about the construction and operation of the technology will be of great benefit for further power grid expansion in the future.”

The line project was successfully completed after less than two years of construction. Almost 5 kilometres of the line were implemented as underground cables. However, even if TenneT can be satisfied with what has been accomplished so far and is strongly committed to expanding the transmission of green electricity throughout its entire grid area, Meyerjürgens sees a need for further action, especially in view of the increasing offshore wind volumes: “Still, we already see today a further demand for expansion in the Wilhelmshaven and Friesland region.”

TenneT commissioned the new Wilhelmshaven-Conneforde line (picture: TenneT)

Linkup
> See TenneT press release, in German (html)