€30m for substation upgrade in Lower Austria

19.05.2020

The grid infrastructure of TSCNET shareholder APG, the Austrian transmission system operator (TSO), must comply with the changes in the power system. The APG projects in this regard are essential for the success of the energy transition and indispensable for Austria’s secure future electricity supply. One example of this is the modernisation of the Ternitz substation in Neunkirchen in Lower Austria, which was built in 1965. With its reconstruction, the TSO significantly improves the power supply of the industrial district south of Vienna, Upper Styria and the Mürztal valley in north-eastern Styria. In addition, a new phase-shifting transformer (PST) will increase failure safety for all of Austria and facilitate the smart integration of green electricity such as wind power from the Weinviertel region into the APG grid. All in all, the TSO is investing €30m in the substation upgrade.

The Ternitz substation is an important hub in APG’s supraregional power grid. Its infrastructural significance is emphasised by the new 220/110kV transformer, which will be one of three such PSTs in Austria. In the 220kV grid, it regulates the flow of electricity on the power lines in north-south direction and distributes it evenly to assure full electricity supply for the region and for all of Austria. To maintain reliability also during the time of the reconstruction, APG will be keeping the substation in operation with numerous temporary measures. Construction was originally scheduled to be concluded in December 2020, but due to the corona pandemic, completion is expected to be delayed by about three months and is now scheduled for March 2021.

Since mid-April, about 50 APG construction projects that were suspended after the Covid outbreak have been gradually resumed in compliance with the necessary distance and hygiene requirements. APG is thus living up to its responsibility not only towards the energy industry, but also as a driving force for the Austrian economy as a whole. In 2020, the investment volume of all APG construction projects in the areas of grid extension, renovation and maintenance projects will total €350m.

APG is investing €30m in the upgrade of the Ternitz substation in Lower Austria (picture: Christoph Breneis / APG)

Linkup
> See APG press release, in German (html)

See article on single page

Demolition makes room for DC substation

14.05.2020

After TransnetBW, the transmission system operator (TSO) from the south-western German state of Baden-Württemberg, was granted building permit for the ULTRANET substation on the site of the former Philippsburg nuclear power plant in March 2020, the way is now finally clear for its construction. At 6.05 in the morning of 14 May 2020, the two cooling towers on the site of the former power plant were detonated. Now the necessary construction space of around 100,000m² is created. The Philippsburg plant was shut down completely on 31 December 2019 and the building construction of the ULTRANET substation is scheduled to start in the third quarter of 2020.

Since the future Philippsburg substation is the southern end point of the supra-regional high-voltage direct current (HVDC) line ULTRANET, it will be one of the most important energy hubs in Germany’s soon-to-be energy landscape. ULTRANET, a European Project of Common Interest (PCI), is jointly implemented by the two TSCNET shareholders TransnetBW and Amprion. It will transfer wind energy generated in the northwest of Germany to the more industrially developed southwest with low losses. In Philippsburg, the transmitted DC will be converted into AC and distributed regionally. In the reverse case, the substation enables the conversion of AC to DC, e.g. to transport excess photovoltaic power from the south to the north.

The fact that the “green” substation will feed renewable electricity into the transmission system instead of nuclear power is a representative of the entire German energy future. “The construction of our DC substation on the site of the cooling towers of the nuclear power plant is a visible sign and symbol of the progress of the energy transition,” comments Dr. Werner Götz, Chairman of the TransnetBW Executive Board. “In future, renewable electricity will flow from the Philippsburg site through the TransnetBW transmission grid to the entire region. Thus, as the TSO in Baden-Württemberg, we ensure that our country will have the electricity it needs even in a future without nuclear power and coal.”

With the cooling towers of the Philippsburg nuclear plant detonated, TransnetBW will begin construction of the ULTRANET substation (picture: screenshot taken from video “Sprengung der Kühltürme des Atomkraftwerks Philippsburg”, in German, YouTube channel of German newspaper “Die Rheinpfalz“)

Linkup
> See TransnetBW press release, in German (html)

See article on single page

Construction of ULTRANET substation approved

27.03.2020

The Philippsburg nuclear power plant in the German state of Baden-Württemberg was shut down completely on 31 December 2019. On the power plant site, TSCNET shareholder TransnetBW, the Transmission System Operator (TSO) from the southwest of Germany, is planning a new DC substation with a required area of around 100,000m². The substation is to become one of the most important energy hubs in Germany’s future energy landscape, as the supra-regional high-voltage direct current (HVDC) line ULTRANET will be connected here to the regional 380kV AC grid.

After intensive planning, TransnetBW submitted the application for construction permit to the competent district administration for examination in June 2018. The Landratsamt Karlsruhe has now approved the plans of the TSO. “The DC substation plays a central role in integrating renewable energies into the transmission grid,” explains Dr. Werner Götz, Chairman of the TransnetBW Executive Board. “In the future, renewable electricity will flow from the Philippsburg site to the entire region. We are thus laying a cornerstone for supply security in a future without nuclear power and coal.”

ULTRANET, a European Project of Common Interest (PCI), is jointly implemented by TransnetBW and the further TSCNET shareholder Amprion. It will transfer wind energy generated in the northwest of Germany to the industrially highly developed southwest. The Philippsburg substation represents the southern end point of ULTRANET. Here, the DC transmitted via ULTRANET to Philippsburg is converted into AC and distributed throughout the region. Vice-versa, the substation allows the conversion of AC into DC, e.g. to transport surplus photovoltaic power from the south to the north.

TransnetBW has received official approval for the construction of the ULTRANET substation in Philippsburg (architectural sketch of the substation: Codema International GmbH / TransnetBW)

Linkup
> See TransnetBW press release, in German (html)

See article on single page

Germany’s first hybrid Statcom facility in operation

27.01.2020

Since January 24, Germany’s first hybrid static synchronous compensator (Statcom) system is connected to the power grid. For about two years, TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO), has been modernising its long-established substation in Borken, in the German state of Hesse, practically at the centre of the German transmission system. The heart of the conversion work was the installation of the Statcom system. Due to the limited space available at the site, TenneT decided to build the Statcom system in hybrid construction, thus reducing the additional space requirement to less than one hectare.

With the high-performance technology in operation, TenneT uses the historic substation in Borken, which boasts a tradition of almost a hundred years, for a task that will contribute significantly to the success of the energy transition: the provision of dynamic voltage support and reactive power to compensate for the decreasing capacities previously provided by large power plants that are being successively shut down. The TSO invested around €30m in the Borken substation, that now has become one of the most modern hubs for green power in the German grid.

Last Friday, Axel Schomberg, Head of TenneT Grid Operations, together with high representatives of local politics, officially commissioned the Statcom system, underlining the significance of the facility for the energy transition. In combination with the numerous other reactive power compensation systems operated in the 129 German TenneT substations, including compensation coils, MSCDN systems and the first rotating phase shifter in the German power grid at the time of installation, the Statcom system contributes to the static reactive power supply.

TenneT has commissioned Germany’s first hybrid Statcom system (picture: TenneT)

Linkup
> See TenneT press release, in German (html)

See article on single page

Swissgrid and hydropower storage plants agree on minimum production

20.12.2019

To avoid an overload of grid elements in western Switzerland during the winter holidays, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), has agreed upon a minimum production with selected regional hydropower storage plants. This is intended to reduce the potential increased and costly need for redispatch during these low-consumption days.

The measure is also necessary because the availability of the transformer at the Bassecourt substation in the canton of Jura is currently limited and the new transformer at Mühleberg in the canton of Berne has not yet been fully installed. Both projects will be implemented in spring 2020. The agreed minimum production in the period from 20 December 2019 to 6 January 2020 is 200MW (off-peak) and 400MW (peak).

Swissgrid has negotiated minimum production from hydropower storage plants

Linkup
> See Swissgrid news release (html)

See article on single page

First pylon of new East Bavarian Ring erected

16.11.2019

The Ostbayernring (East Bavarian Ring) is an existing power line operated by the Dutch-German transmission system operator (TSO) TenneT, that stretches about 185km from the Upper Franconian town of Redwitz via Mechlenreuth and Etzenricht to Schwandorf in the Upper Palatinate. After the shutdown of Northeast Bavarian nuclear and conventional power plants, the Ostbayernring primarily transports renewable energies. On several days of the year, more energy is generated by wind turbines and photovoltaic plants in the regions along the East Bavarian Ring than is needed locally. Due to the resulting increase in the amount of renewable energy fed into the grid, the East Bavarian Ring regularly reaches its capacity limits.

To ensure the security of supply and the reliability of the grid and to prevent grid failures for the entire region of Upper Franconia and Upper Palatinate, the transmission capacities of the East Bavarian Ring need to be significantly improved. A replacement construction for the East Bavarian Ring was therefore included in the German Federal Requirements Plan and the urgency of the project for the energy market was legally determined. The new line is being constructed along the existing route, extending the current 380/220kV systems to two 380kV systems.

In the course of the construction of the new East Bavarian Ring and the related grid reinforcement, the Redwitz, Mechlenreuth, Etzenricht and Schwandorf substations of the TSCNET shareholder are also being upgraded. Now the first pylon of the new Ostbayerring has been erected on the site of the Etzenricht substation. TenneT has captured the construction on film in order to give a well-founded impression of the erection process.

The first pylon of the new East Bavarian Ring of TenneT has been erected (picture: TenneT / screenshot taken from TenneT-video “TenneT Ostbayernring: Der Projektleiter stellt sich vor”, YouTube)

Linkup
> See TenneT tweet, in German (html)
> Watch video of the pylon construction (YouTube)

See article on single page

GIS with Clean Air technology for Daxlanden

14.11.2019

In present-day gas-insulated high-voltage systems, sulfur hexafluoride (SF6) is commonly used as insulating gas. It has excellent electrical and chemical properties, but also a strong greenhouse effect. For reasons of climate protection, TransnetBW, one of the four German transmission system operators (TSOs), focuses on eco-efficient technical concepts. In November last year, the TSCNET shareholder launched a pilot project at its substation in Obermooweiler, northeast of Lake Constance, with the world’s first gas-insulated switchgear (GIS) at extra-high voltage level using a climate-friendly alternative gas technology.

TransnetBW has now commissioned the new construction of the switchgear for the 380kV substation in Daxlanden near Karlsruhe, where the existing open-air facility will be replaced by two new GIS. Here, the TSO has opted for the so-called Clean Air technology, which exclusively uses processed air as an insulating medium instead of SF6. This significantly reduces the greenhouse effect of the entire switchgear system. The new GIS facilities will be built and commissioned gradually over the next few years and the existing open-air installation will be dismantled during ongoing operation.

The Daxlanden substation is an important network node in TransnetBW’s transmission grid and the central link between two grid construction projects from the German national Grid Development Plan for electricity (NEP), which contains essential grid extension projects to realise the energy transition. “A successful energy transition requires an efficient and future-proof transmission grid,” explains Dr. Werner Götz, Chairman of the TransnetBW Executive Board. “The more we are pleased to be able to make an additional contribution to the environment and climate protection by using the innovative Clean Air technology in Daxlanden.”

TransnetBW will build two GIS with Clean Air technology in the substation Daxlanden (computer simulation of the reconstructed Daxlanden substation: TransnetBW)

Linkup
> See TransnetBW press release, in German (html)

See article on single page

New Amprion phase shifter in operation

06.11.2019

The German transmission system operators (TSOs) have to react with innovative technology to the changes in the German energy landscape caused by the shutdown of nuclear and other large power plants in the course of the energy transition. An important issue is the loss of reactive power, and an appropriate technological response are rotating phase shifters, which are highly efficient and flexible in the provision of reactive power to maintain voltage.

TSCNET shareholder Amprion has now commissioned such a high-performance system at its Illingen-Uchtelfangen substation in the German federal state of Saarland. It is the second rotating phase shifter in the Amprion grid after the TSO commissioned the first one in September 2018 in Oberottmarshausen (Bavarian Swabia). Amprion has invested €60m in the new state-of-the-art equipment, which keeps the transmission grid stable and thus further increases supply security in Saarland.

The commissioning ceremony was attended by Anke Rehlinger, Saarland Minister for Economic Affairs, Labour, Energy and Transport. Together with Amprion Managing Director Dr. Klaus Kleinekorte, General Manager of GE Grid Solutions Gerhard Seyrling and representatives of district and municipal politics, she pressed the “red button”, which symbolically put the facility into operation. Mrs Rehlinger commented on the new device: “Against the backdrop of the energy transition, grid stability and security of supply are becoming increasingly important. With the installation of the rotating phase shifter, Amprion is making an important contribution to the future of power transmission grids.”

Amprion has commissioned a new rotating phase shifter at the Illingen-Uchtelfangen substation (picture: Amprion;  Amprion CTO Klaus Kleinekorte and Saarland Minister Anke Rehlinger in the middle)

Linkup
> See Amprion press release, in German (html)

See article on single page

Two transformers reach Garenfeld

05.11.2019

The last weekend was literally “heavy” for TSCNET shareholder Amprion, one of the four German transmission system operators (TSOs). Not one but two 276-tonne transformers were transported to Amprion’s Garenfeld substation in Hagen in North Rhine-Westphalia. It took both days of the weekend for the 30 kilometre stretch from the railway station to the substation. The special road transport units each had a total length of around 80 metres and together with the transformer each weighed 519 tonnes.

About 40 employees from various companies were involved in the transport during the two nights. At the end of August, the first of a total of five transformers had already been delivered to the substation. Amprion is currently planning to move the last two transformers to Garenfeld at the end of November.

Two transformers have been delivered to the Garenfeld substation operated by Amprion (picture: Amprion)

Linkup
> See last week’s announcement press release, in German (html)
> See Amprion tweet, in German (html)

See article on single page

Ernen-Ulrichen 380kV line in operation

21.10.2019

With the erection of the last of a total of 57 pylons, the new extra-high voltage line between the Ernen and Ulrichen substations in the Swiss canton of Valais has now been completed. The 30-kilometre section is part of the 380kV Mörel-Ulrichen line project of TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO). The line upgrade in the Rhône Valley is vital for the future of Switzerland’s energy supply: In order to fully transfer the hydropower generated in the Valais to the urban areas of Switzerland, the lines of the south-western canton must be connected to the supra-regional 380kV transmission grid, particularly in view of the commissioning of the new Nant de Drance pumped storage power station, scheduled for 2020.

The existing 220kV overhead line between Ernen and Ulrichen is already disconnected. Its 177 pylons will be dismantled from spring 2020 and the former pylon locations will be recultivated. Swissgrid is additionally carrying out nature conservation projects of national importance in the vicinity of the new line. Also starting next year, the Swiss TSO will continue its Valais upgrade project with the new construction of the next section between Ernen and Mörel-Filet, which is expected to be commissioned as 380kV line by the end of 2022.

Swissgrid has commissioned the new 380kV line between Ernen-Ulrichen (picture: Swissgrid)

Linkup
> See Swissgrid news release, in German (html)

See article on single page