€215m for green connection capacity

11.10.2019

The Dutch-German transmission system operator (TSO) TenneT plans to invest a further €215m to connect two GW of green electricity from solar and wind farms in the north of the Netherlands to the grid. The infrastructural measures include the construction of two new 380/110kV high-voltage substations in the provinces of Groningen and Drenthe. In addition, the TSCNET shareholder intends to provide extra capacity at nine existing 110kV substations in the northern Netherlands.

One GW corresponds roughly to the output of 3.5 million solar modules or 200 wind turbines. The additional capacity planned by the TSO is therefore considerable, but according to Ben Voorhorst, COO of the TSO, as many solar and wind farm transmission requests as possible should be complied with. Already now TenneT operates projects in the northern Netherlands with a volume of more than €1bn. This level of investment is now being further increased, with the TSO focusing strongly on the sustainability and efficiency of the investments. “The better the capacity expansions of electricity grids are actually utilised, the better the consumer’s money is spent,” explains Voorhorst.

TenneT invests €215m in the connection of renewable energies in the northern Netherlands (picture: TenneT)

Linkup
> See TenneT press release (html)

See article on single page

New Nordic System Operation Agreement

04.10.2019

The five Nordic power transmission system operator (TSOs), including the Danish TSCNET shareholder Energinet, have signed a new Nordic System Operation Agreement. This agreement sets out the common operating principles of the Nordic TSOs to ensure that the Nordic interconnected system is operated reliably and efficiently in accordance with national and European regulations.

Against the background of the increasing volatility of electricity generation due to renewable energies and the reduction of balancing power generation, the Operating Agreement will further strengthen Nordic cooperation, harmonise grid operating practices between Nordic countries and within Europe, and ensure the system security of the Nordic electricity system.

The document will also contain several appendices, of which the appendix on reserves has already been concluded. The Nordic TSOs are in the process of finalising further appendices on all relevant operational issues. The new Operation Agreement will successively replace the existing one after the completion of the new appendices.

Energinet and the other four Nordic TSOs have signed a new Nordic System Operation Agreement (picture showing Copenhagen, Denmark)

Linkup
> See Energinet press release (html)
> Open Nordic System Operation Agreement (pdf, 894.16kB)

See article on single page

Central project management and office for SuedLink

24.09.2019

The SuedLink extra-high voltage line is not only the most important individual project of the energy transition in Germany, but also the largest underground cable project in the world: Around 700 kilometers of cable will be laid and around ten billion euros invested. By connecting the windy regions of northern Germany with the consumption centres in the industrially highly developed south, “power highways” such as SuedLink are indispensable for achieving Germany’s and Europe’s climate goals. SuedLink is implemented jointly by the two TSCNET shareholders TenneT, the Dutch-German transmission system operator (TSO), and TransnetBW, the TSO from southwest Germany.

In order to efficiently advance the further approval procedure and the subsequent construction of SuedLink, the two TSOs have commissioned the international technical service company Jacobs as central service provider. The aim is to coordinate and control the various tasks such as planning, approval, obtaining easements and construction under one roof. This makes SuedLink the first major project in Germany in which an external central service provider is involved. TenneT Managing Director Tim Meyerjürgens explains why the two partners decided on a model that has proven itself many times in such large-scale projects on the international market: “The schedule for implementation is challenging. At the same time, the expectations of politics and the public continue to rise. For this very reason, controlling and coordination play such an important role.”

The commissioning of Jacobs is accompanied by the opening of the central SüdLink office in Würzburg, Lower Franconia. Together with the central service provider, TransnetBW and TenneT will initially create 130 jobs there, the number of which will rise to 250 in the course of the project. To better incorporate regional knowledge into the planning process, further decentralised project offices are to follow along the route. Dr. Werner Götz, Chairman of the TransnetBW Executive Board, comments on the development: “By commissioning a central service provider and setting up a joint project facility in Würzburg, we have laid the foundations for the successful implementation of this major project.” The staff in Würzburg will include engineers, archaeologists, landscape planners, biologists, geologists, and project managers, all joining forces for Europe’s energy future.

TenneT and TransnetBW commission a central service provider for the implementation of SuedLink (picture: TenneT / Katja Schubert)

Linkup
> See TenneT press release, in German (html)
> See TransnetBW press release, in German (html)
> See TransnetBW press release on the office opening, in German (html)

See article on single page

Danish wind power generation exceeds demand

23.09.2019

Sunday, 15 September 2019, now is a historical date for the Danish electricity market. Within the 24 hours of that day and during the first strong autumn winds of the year, wind power generation covered 130 percent of national demand, thus exceeding it for the first time for an entire day. According to preliminary figures from TSCNET shareholder Energinet, the Danish power transmission system operator (TSO), Danish wind turbines generated between 2 a.m. and 3 a.m. early Sunday morning an impressive 60 percent more electricity than the Danish market actually consumed.

For one thing, this beats the previous record of 9 June 2019 (52 percent above demand), but what is even more significant for the Danish energy transition is this being the first 24-hour period ever in which surplus wind energy has been generated during all day and night hours. This surplus wind energy was further transmitted by Energinet and sold to other countries.

Carsten Vittrup, Energy Strategy Adviser at Energinet, comments on these groundbreaking figures: “A mere ten years ago, wind accounted for only about one fifth of our supply. But things have developed extremely fast, meaning that we now see not just hours, but entire days of wind turbines generating more electricity than we need.”

Energinet reports record in national wind power generation (picture: Energinet)

Linkup
> See Energinet press release (html)

See article on single page

50 new pylons for the Pradella-La Punt line

19.09.2019

The extra-high voltage line in the Swiss Engadine between Pradella/Scuol and La Punt represents a bottleneck in the Swiss and the European transmission grid. To remedy this shortcoming, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), began upgrading the 380kV line to 2 x 380kV in October 2017. This will increase import capacity from the north, strengthen interconnections with Austria and Italy and facilitate the transport of hydropower in the canton of Grisons. The project also improves security of supply in Switzerland and is part of the “Strategic Grid 2025”, Swissgrid’s ambitious modernisation and expansion plan.

Basically, the upgrade means that Swissgrid will attach a second 380kV line to the pylons, which are originally fitted with only one line on one side. Over the past two years, the TSO has reinforced the mast foundations between Pradella and La Punt and will complete this work in autumn. But Swissgrid has also examined the static of the pylons and discovered that some of them have insufficient load capacity for the second circuit. For safety reasons, it was thus decided to replace 50 of altogether 127 masts instead of reinforcing them. This change has no impact on the routing, but on the schedule: The commissioning of the upgraded line will be delayed by at least one year and is now planned for 2022.

Swissgrid has to erect 50 new pylons for the Pradella-La Punt line (picture: Swissgrid)

Linkup
> See Swissgrid news release (html)

See article on single page

Reconstruction start at TransnetBW substation

18.09.2019

On September 18, TSCNET shareholder TransnetBW, one of the four German transmission system operators (TSOs), started the conversion of its substation in Schwörstadt with a symbolic cut of the spade. The construction site is located in the furthest southwest of the German federal state of Baden-Württemberg near the Swiss border. The upgrade provides the technical basis for connecting the substation to the 380kV extra-high voltage grid.

Dr. Werner Götz, Chairman of the TransnetBW Executive Board, referred at the groundbreaking ceremony to the steadily increasing share of renewables in the electricity mix, which confronts TSOs with maintaining voltage at a stable level despite the changing wind and weather conditions. “We are preparing the substation for the requirements of the energy transition and thus are also strengthening supply security in the Upper Rhine region.”

The reconstruction of the substation’s switchgear will be carried out in two stages, starting with the dismantling of the operations building and the switch panels of the existing 220kV switchgear. By 2021, the new 380kV switchgear will have been installed. The new device will initially be operated at 220kV before being connected to the 380kV grid in 2023. This implies that at the same time and section by section, the corresponding power lines will also be upgraded to 380kV.

TransnetBW starts conversion of the Schwörstadt substation (picture: TransnetBW; from left to right: Olaf Jungnitsch of GE Grid; Uli Glich, Project Manager Substations at TransnetBW; Christine Trautwein-Domschat, Mayor of Schwörstadt; Dr. Werner Götz, Chairman of the TransnetBW Executive Board; Thorsten Schwarz, Managing Director GE Grid; Bernd Jauch, Head of Technology, Projects and Portfolio Management at TransnetBW)

Linkup
> See TransnetBW press release, in German (html)

See article on single page

Final Conference of FutureFlow

10.09.2019

The FutureFlow project reaches the final straight: On 15 October, the Slovenian transmission system operator (TSO) ELES will host the final conference of the successful project in the Austrian capital of Vienna. FutureFlow was launched in 2016 and funded by the EU under the Horizon 2020 programme. The twelve project partners from eight European countries will officially conclude the project in December 2019.

The increasing regenerative energy generation and decreasing flexibility from conventional power plants require innovative approaches by the players in the electricity market. This is where the FutureFlow project comes in by exploring innovative e-trading solutions for smart cross-border balancing and redispatching in the control areas of four central-south European TSOs, all shareholders of TSCNET. In addition to the project coordinator ELES, the other TSO participants are APG from Austria, MAVIR from Hungary and Transelectrica from Romania.

At the final conference the FutureFlow partners will present the most important project results and options for their implementation. These include, for example, the real-time results of the cross-border pilot tests and the operation of the IT platforms developed as part of FutureFlow.

The final conference of the FutureFlow project is hosted by Eles in Vienna on 15 October (picture: Stefan Steinbauer, Pixabay)

Linkup
> See ELES press release (html)
> Visit FutureFlow website (html)
> Visit FutureFlow conference website (html)

See article on single page

Borssele Alpha ready to operate

05.09.2019

Just one month ago, TSCNET shareholder TenneT fully implemented BorWin3 in the German Bight, the twelfth offshore grid connection project of the Dutch-German transmission system operator (TSO). Now there is once again good news for the energy transition, this time from the Dutch North Sea: Borssele Alpha, TenneT’s first and largest connection system for wind farms in Dutch territorial waters, is ready for operation – right on schedule and within budget. From 2020 on, Borssele Alpha will supply the green electricity from the offshore wind farms Borssele I and II ashore.

The two Borssele wind farms will have a capacity of around 700MW. The Borssele Alpha grid connection will transmit the electricity to the substation near the town of Borssele in the Dutch province of Zeeland, where TenneT has built a new transformer station next to the existing station. The Borssele grid connection is TenneT’s first Dutch major project under the National Energy Agreement for offshore wind farms and fully complies with the conditions set out in the Dutch government’s Offshore Wind Energy Development Framework.

According to the Energy Agreement, TenneT will have installed 3,500MW of grid connections for offshore wind farms by the end of 2023. The next project is Borssele Beta, followed by Hollandse Kust (zuid) Alpha and Beta and Hollandse Kust (noord). TenneT’s standardised procedure for offshore connections will make it possible to complete these projects more efficiently, quickly and economically. In line with the Dutch Follow-up Roadmap for Offshore Wind Energy, a further 6,100MW of offshore wind energy will be realised between 2024 and 2030.

The Borssele Alpha offshore grid connection of TenneT is operational (picture: Screenshot taken from the Borssele video)

Linkup
> See TenneT press release (html)
> Watch TenneT video “Opening Borssele Trailer Master” (YouTube)

See article on single page

COBRAcable market launch on 7 September

02.09.2019

After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule. The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO.

The high-voltage DC cable with a length of about 325km has a capacity of 700MW. The Netherlands can import more sustainable electricity from Denmark through COBRAcable, mainly wind energy. In addition, the cable provides Dutch capacity on a structural basis for the Danish electricity grid, thus ensuring security of supply in Denmark, which of course also works the other way round. Moreover, the cable connection is designed in such a way that an offshore wind farm can be connected at a later date, so that COBRAcable contributes to a sustainable European energy landscape.

The COBRAcable interconnector of Energinet and Tennet is available to the market from 7 September (picture: screenshot taken from TenneT-video “First pile COBRAcable”, YouTube)

Linkup
> See TenneT press release (html)

See article on single page

BorWin3 in operation

12.08.2019

The offshore grid connection BorWin3 operated by TSCNET shareholder TenneT in the German Bight is ready for feed-in since early August. This means that the total transmission capacity for offshore wind farms in the German North Sea is already 7.132GW. The Dutch-German transmission system operator (TSO) has thus not only met the German government’s expansion targets for sustainable North Sea wind power – 6.5GW by 2020 – but has significantly exceeded them.

BorWin3, TenneT’s twelfth offshore grid connection project, brings a further 900MW capacity. After BorWin1 and BorWin2, it is the third connection that the TSO has implemented near the East Frisian island of Borkum using DC technology. The corresponding converter and transformer station were built at TenneT’s Emden/Ost site to feed the green energy into the onshore extra-high voltage grid. BorWin3 bridges a total distance of 160km. The submarine cable is 130km long and the last section ashore to Emden/Ost is completed by underground cabling.

The TSO can be satisfied with its own offshore progress, but TenneT Managing Director Tim Meyerjürgens calls for further efforts, as the current rate of offshore wind expansion in Europe is not sufficient to achieve the goals of the Paris Climate Agreement. “An accelerated, large-scale and internationally coordinated expansion is necessary,” explains Meyerjürgens. In this context, TenneT has just presented a feasibility study of the North Sea Wind Power Hub concept for the implementation of wind power distribution hubs in the North Sea. Meyerjürgens points out that with an internationally coordinated approach the connection and integration of large offshore wind energy capacities could be much more effective and cost-efficient than with continued individual national planning.

In early August, the offshore grid connection BorWin3 of TenneT was put into operation (picture of the offshore converter platform BorWin gamma: TenneT)

Linkup
> See TenneT press release, in German (html)

See article on single page