Swift progress for new 50Hertz overhead line

29.11.2019

This May, TSCNET shareholder 50Hertz, one of the four German transmission system operators (TSOs), started the construction of the first section of the 380kV Perleberg-Wolmirstedt overhead line. The new line will connect the Perleberg substation in Brandenburg with the Wolmirstedt substation in Saxony-Anhalt over a distance of 106km and replace the existing 220kV line from the 1950s. This grid extension is intended to ensure that the increasing quantities of regionally generated electricity from renewable sources are also available to consumers in southern and western Germany.

The first construction phase with 87 pylons and a length of 37km stretches between the substations Stendal West and Wolmirstedt. Construction work is progressing rapidly. More than half of the pylons have now been erected and some masts have already been fitted with power cables. Construction should be completed by mid-March next year.

50Hertz has already erected 48 pylons of the Perleberg-Wolmirstedt overhead line (picture of the substation Wolmirstedt: Otto-von-Guericke-Universität Magdeburg)

Linkup
> See 50Hertz press release, in German (html)

See article on single page

Kick-off for new Weinviertel Line

19.11.2019

The Weinviertel Line (“Weinviertelleitung”) in Lower Austria is in operation for more than 70 years. An elementary component of the grid of TSCNET shareholder APG, the Austrian transmission system operator (TSO), the 220kV line is now in considerable need of rehabilitation. Apart from that, the routing of the existing line does not meet the requirements of the future energy system characterised by decentralised generation of the renewables. The Weinviertel Line reconstruction is therefore essential for the implementation of the Austrian energy and climate strategy “#mission2030”, which sets the national goal of covering 100% of electricity consumption with renewable energies by 2030.

The new 380kV Weinviertel Line will run from Seyring near Vienna to the substation in Neusiedl an der Zaya in the north-eastern Weinviertel. Here in Neusiedl, the ground-breaking ceremony for the new construction has now taken place. To the benefit of the environment and local residents, the new Weinviertel line requires 53 pylons less than the old one. “This is because we can dismantle the first eleven kilometres of the old line without replacement, as we will connect the new line with an existing line and feed it in there,” explained Gerhard Christiner and Thomas Karall, CTO and CFO of APG respectively. The investment costs for the new line amount to 200m euros.

Christiane Teschl-Hofmeister, a member of the Lower Austrian state government who attended the ceremony, commented: “With the new APG Weinviertel Line, Lower Austria will have an efficient and future-oriented grid connection for renewable energies from the region. The APG Weinviertel Line thus makes an important contribution to the Lower Austrian Climate and Energy Roadmap 2030.”

APG has started construction of the new Weinviertel Line (picture: APG; from left to right: Franz Mittermayer from Austrian energy company EVN, Thomas Karall, Christiane Teschl-Hofmeister and Gerhard Christiner)

Linkup
> See APG press release, in German (html)

See article on single page

First pylon of new East Bavarian Ring erected

16.11.2019

The Ostbayernring (East Bavarian Ring) is an existing power line operated by the Dutch-German transmission system operator (TSO) TenneT, that stretches about 185km from the Upper Franconian town of Redwitz via Mechlenreuth and Etzenricht to Schwandorf in the Upper Palatinate. After the shutdown of Northeast Bavarian nuclear and conventional power plants, the Ostbayernring primarily transports renewable energies. On several days of the year, more energy is generated by wind turbines and photovoltaic plants in the regions along the East Bavarian Ring than is needed locally. Due to the resulting increase in the amount of renewable energy fed into the grid, the East Bavarian Ring regularly reaches its capacity limits.

To ensure the security of supply and the reliability of the grid and to prevent grid failures for the entire region of Upper Franconia and Upper Palatinate, the transmission capacities of the East Bavarian Ring need to be significantly improved. A replacement construction for the East Bavarian Ring was therefore included in the German Federal Requirements Plan and the urgency of the project for the energy market was legally determined. The new line is being constructed along the existing route, extending the current 380/220kV systems to two 380kV systems.

In the course of the construction of the new East Bavarian Ring and the related grid reinforcement, the Redwitz, Mechlenreuth, Etzenricht and Schwandorf substations of the TSCNET shareholder are also being upgraded. Now the first pylon of the new Ostbayerring has been erected on the site of the Etzenricht substation. TenneT has captured the construction on film in order to give a well-founded impression of the erection process.

The first pylon of the new East Bavarian Ring of TenneT has been erected (picture: TenneT / screenshot taken from TenneT-video “TenneT Ostbayernring: Der Projektleiter stellt sich vor”, YouTube)

Linkup
> See TenneT tweet, in German (html)
> Watch video of the pylon construction (YouTube)

See article on single page

TenneT quadruples capacity across the Elbe

29.10.2019

A new Elbe crossing between the German federal states of Schleswig-Holstein and Lower Saxony for the transport of green electricity from North to South Germany has been completed. Tim Meyerjürgens, COO of the Dutch-German transmission system operator (TSO) TenneT, together with the State Secretaries Andreas Feicht and Enak Ferlemann, the Energy Ministers Olaf Lies (Lower Saxony) and Jan Philipp Albrecht (Schleswig-Holstein), has commissioned the new power line between the substations Hamburg/Nord (near Norderstedt/Schleswig-Holstein) and Dollern (Lower Saxony).

The new 380kV line of the TSCNET shareholder consists of four sections and is a replacement of existing lines with predominantly lower voltage levels to meet the requirements of the energy transition. A total of 110 masts were built or modified and 37 temporary masts were erected on several sections of the line. Almost all of them have now been dismantled. The installation of new conductor ropes at “Elbe Crossing 2” which has the highest pylons in Europe with a height of 227 meters, was also part of this demanding grid expansion project.

Tim Meyerjürgens explained on the occasion of the commissioning: “The extension of the 45-kilometre-long power line is an important component of the energy transition. This also includes the optimisation of the ‘Elbe Crossing 2’, the main artery in the three-phase transmission grid between Schleswig-Holstein and Lower Saxony, which serves as a bridge between the two largest wind power states in Germany.” With these reconstruction measures, Tennet has quadrupled the available capacity for the transmission of wind power in this area to 9.6 GW. The transit capacity between Denmark and Germany will also be increased, which is why the new connection is of central importance not only for the energy transition in Germany, but also at European level.

Picture: TenneT

TenneT has put new power line across the Elbe into operation (picture: TenneT; from left to right: TenneT COO Tim Meyerjürgens; Olaf Lies, Lower Saxony Minister for the Environment, Energy, Construction and Climate Protection; Jan Philipp Albrecht, Schleswig-Holstein Minister of Energy, Agriculture, the Environment, Nature and Digitalisation; Parliamentary State Secretary Enak Ferlemann; Andreas Feicht, State Secretary at the Federal Ministry for Economic Affairs and Energy)

Linkup
> See TenneT press release, in German (html)

See article on single page

Ernen-Ulrichen 380kV line in operation

21.10.2019

With the erection of the last of a total of 57 pylons, the new extra-high voltage line between the Ernen and Ulrichen substations in the Swiss canton of Valais has now been completed. The 30-kilometre section is part of the 380kV Mörel-Ulrichen line project of TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO). The line upgrade in the Rhône Valley is vital for the future of Switzerland’s energy supply: In order to fully transfer the hydropower generated in the Valais to the urban areas of Switzerland, the lines of the south-western canton must be connected to the supra-regional 380kV transmission grid, particularly in view of the commissioning of the new Nant de Drance pumped storage power station, scheduled for 2020.

The existing 220kV overhead line between Ernen and Ulrichen is already disconnected. Its 177 pylons will be dismantled from spring 2020 and the former pylon locations will be recultivated. Swissgrid is additionally carrying out nature conservation projects of national importance in the vicinity of the new line. Also starting next year, the Swiss TSO will continue its Valais upgrade project with the new construction of the next section between Ernen and Mörel-Filet, which is expected to be commissioned as 380kV line by the end of 2022.

Swissgrid has commissioned the new 380kV line between Ernen-Ulrichen (picture: Swissgrid)

Linkup
> See Swissgrid news release, in German (html)

See article on single page

Randstad 380kV North Ring in operation

14.10.2019

The four largest Dutch cities (Amsterdam, Rotterdam, The Hague and Utrecht) and their surroundings constitute the Randstad region in the Netherlands. With a population of more than 8 million people, it is Europe’s most densely populated area. Randstad has a high energy demand, which needs to be reliably met and secured also in the future. However, infrastructure construction measures are particularly challenging in such a conurbation. TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO), has now made an elementary contribution to security of supply of the Randstad.

After a construction period of five years, the 60-kilometer-long Randstad 380kV North Ring power line was put into operation on 10 October. More than 1000 people from the region, 300 landowners, over 25 responsible authorities, 13 contractors and 200 TenneT employees were involved in its construction. The new high-voltage line will reliably supply millions of households and companies with electricity. It will also provide the transmission capacity required for green electricity from North Sea wind farms. As a complementary measure, the existing 150kV connections in the region were adapted and two new high-voltage substations have been built in Beverwijk and Vijfhuizen.

At 151 locations along the route, Tennet installed innovative Wintrack pylons that consume less space, reduce magnetic field zones and, due to their slim and streamlined shape, fit much better into their surroundings than conventional steel lattice pylons. Ten kilometres of the North Ring have been laid underground. The aluminium cables used by TenneT are a novelty. They are cheaper than conventional materials and conduct electricity more efficiently, which means that their carbon footprint is smaller.

TenneT has commissioned the Randstad 380kV North Ring (picture of the opening ceremony with TenneT CEO Manon van Beek and COO Ben Voorhorst: TenneT)

Linkup
> See TenneT press release (html)

See article on single page

Delay for the Bassecourt-Mühleberg line upgrade

07.10.2019

With the decommissioning of the Mühleberg nuclear power plant in the canton of Bern at the end of 2019, part of Switzerland’s energy production in the central Swiss Plateau will cease. In the medium term, this shortage will have to be offset by higher production from Swiss power plants or by energy imports from abroad. This is particularly important in winter, when Switzerland is dependent on additional energy imports.

TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), is therefore upgrading the Bassecourt-Mühleberg power line from 220kV to 380kV and equipping the Mühleberg substation with a new 380/220kV transformer to ensure security of supply in the greater Bern area and the entire central region of the Swiss Plateau. The modernisation of the line will require adjustments to 54 of a total of 142 existing pylons and will not affect the landscape. Both upgrade measures are part of the “Strategic Grid 2025”, Swissgrid’s ambitious grid modernisation and expansion plan.

While the installation work for the new transformer in Mühleberg continues, a delay of two years in the voltage increase of the Bassecourt-Mühleberg line is expected due to legal complaints against the line upgrade. In August, the Swiss Federal Office of Energy approved the line upgrade and rejected the objections, which mainly concerned the exposure to magnetic fields and noise or the need to relocate the line or to use underground cables. Various complainants have now appealed against this decision of the Federal Office to the Federal Administrative Court of Switzerland, thus preventing further progress.

The upgrading of the Bassecourt-Mühleberg power line by Swissgrid will be delayed (picture: Swissgrid)

Linkup
> See Swissgrid media release (html)

See article on single page

50 new pylons for the Pradella-La Punt line

19.09.2019

The extra-high voltage line in the Swiss Engadine between Pradella/Scuol and La Punt represents a bottleneck in the Swiss and the European transmission grid. To remedy this shortcoming, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), began upgrading the 380kV line to 2 x 380kV in October 2017. This will increase import capacity from the north, strengthen interconnections with Austria and Italy and facilitate the transport of hydropower in the canton of Grisons. The project also improves security of supply in Switzerland and is part of the “Strategic Grid 2025”, Swissgrid’s ambitious modernisation and expansion plan.

Basically, the upgrade means that Swissgrid will attach a second 380kV line to the pylons, which are originally fitted with only one line on one side. Over the past two years, the TSO has reinforced the mast foundations between Pradella and La Punt and will complete this work in autumn. But Swissgrid has also examined the static of the pylons and discovered that some of them have insufficient load capacity for the second circuit. For safety reasons, it was thus decided to replace 50 of altogether 127 masts instead of reinforcing them. This change has no impact on the routing, but on the schedule: The commissioning of the upgraded line will be delayed by at least one year and is now planned for 2022.

Swissgrid has to erect 50 new pylons for the Pradella-La Punt line (picture: Swissgrid)

Linkup
> See Swissgrid news release (html)

See article on single page

Romanian legislation promotes energy infrastructure

21.06.2019

In Romania, a new law adopted by President Klaus Iohannis on 20 June facilitates nationally important extensions to the transmission system infrastructure. The act promotes the implementation of important investment projects for Romania’s energy security, the construction of overhead lines and compliance with time limits for projects with European financing.

The Romanian transmission system operator (TSO) and TSCNET shareholder Transelectrica expressly welcomes the new legislation. Marius Dănuţ Carașol, chairman of the Transelectrica Directorate, highlights the positive effects on the TSO’s expansion efforts, for example by reducing bureaucratic obstacles.

New Romanian legislation facilitates grid extension (picture showing the Parliament building in Romania’s capital Bucharest: Mari Ana / Pixabay)

Linkup
> See Transelectrica press release, in Romanian (html)

See article on single page

Line upgrade in the German Upper Rhine Plain

11.05.2019

The transmission capacity of the extra-high voltage grid in the southwest of Baden-Württemberg, Germany, is reaching its limits considering the requirements for an efficient and future-proof energy system. To increase capacity and ensure regional security of supply as well as reliable transmission in the future, Baden-Württemberg’s transmission system operator (TSO), TSCNET shareholder TransnetBW, is replacing the 220kV overhead line between Karlsruhe-Daxlanden and Eichstetten am Kaiserstuhl (near Freiburg) with a 380kV line. This line upgrade in the Upper Rhine Plain is part of the National Network Development Plan for Electricity and comprises the construction of around 120km of new lines and five substations.

The entire project is divided into four sections and the planning approval procedure for the section B1 between Sasbach and Offenburg-Weier in the Ortenau district was opened on 9 May. TransnetBW had submitted the relevant documents at the end of last year to the Freiburg Regional Council. After official review and a revision by the TSO, the authority initiated the approval procedure. Next steps include the consultation process with a month-long disclosure of the documents to the municipalities concerned and the involvement of public interest parties.

Start of planning approval for the Sasbach-Offenburg section of TransnetBW’s Daxlanden-Eichstetten line upgrade (picture: TransnetBW)

Linkup
> See TransnetBW press release, in German (html)

See article on single page