Borssele Beta platform topside ready for sail out

20.03.2020

In the Borssele offshore wind farm area in the south-western part of the Dutch North Sea, Borssele Alpha, the first and largest connection system for wind farms from the Dutch-German transmission system operator (TSO) TenneT in Dutch territorial waters, is already in operation. Now the TSCNET shareholder is in the process of installing Borssele Beta to connect further wind farms, in this case Borssele III and IV that are still under construction. The topside of the offshore transformer platform for Borssele Beta is now ready for shipping. It was built at the construction yard of the offshore platform specialist HSM Offshore in Schiedam in the Rotterdam-The Hague metropolitan area and will be put to sea on 22 March 2020.

When the pontoon carrying the 3,650-tonne superstructure arrives at its destination, a crane vessel will place the top side on the platform substructure (jacket). The top side comprises three interior levels and an outer deck. It is 25 metres high, 58 metres long and 32 metres wide. The Borssele Beta grid connection will have a capacity of 700MW and is scheduled to be commissioned on 1 September 2020. The Borssele III, IV, and V wind farms, which are located about 22km from the coast, will be connected to this transmission system. Borssele V by the Two Towers consortium has been designated as an innovation site within the wind farm zone and will be connected to Borssele Beta. The electricity generated by these offshore wind farms will then be transported ashore via two 67-kilometre-long cables to the high-voltage transformer station near the town of Borssele in the Dutch province of Zeeland.

Marco Kuijpers, Director Offshore Projects a TenneT, comments on the TSO’s progress in offshore expansion: “With this platform, the offshore grid that TenneT is building in the Dutch North Sea is definitively taking shape. Borssele Beta is the second offshore grid connection built by TenneT. Over the coming eight years we will build a new offshore connection every year. I am proud that we are able to make such a significant contribution to the energy transition in which offshore wind energy plays a crucial role.”

TenneT also assumes a marine ecological responsibility and makes its offshore platforms available for other uses. The TSO cooperates in this respect with the Dutch Directorate-General for Public Works and Water Management (Rijkswaterstaat). The Borssele Beta offshore platform therefore also features a Maritime Information Provision Service Point (MIVSP). This is a monitoring station with various monitoring systems, such as nautical radars, meteorological systems and ecological monitoring systems. Similar stations are being installed on every TenneT offshore transformer platform.

The topside of the offshore transformer platform Borssele Beta of TenneT is constructed and ready for shipping (picture: HSM Offshore)

Linkup
> See TenneT press release (html)

See article on single page

TenneT creates, invests and researches for the energy future

12.03.2020

Promoting the energy transition is a priority objective of TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO). This is clearly reflected in the TSO’s just-published Integrated Annual Report. As in recent years, the Annual Report is accompanied by the Green Finance Report 2019.

In line with the energy policy and climate goals of the Netherlands and Germany, TenneT increased its investments yet again in 2019 and spent €3.1bn on the energy transition and supply security (grid availability of 99.9998% in 2019). This financial commitment is even to be stepped up: TenneT is planning annual investments of €4bn to €5bn for the future. The financial performance of the company, with revenues of €4.1bn in 2019 and an EBIT (excluding special effects) of €753m, supports these ambitious plans. Manon van Beek, CEO of TenneT, has every reason to be content with the sound development of the TSO: “We have made great strides again in pursuing our ambition to achieve a sustainable energy future for everyone. Not only in realising and developing new onshore and offshore connections, but also by the required far-reaching international cooperation and working on innovations in close coordination with relevant stakeholders.”

As regards offshore connections, TenneT has already exceeded in 2019 the German government’s expansion target for offshore wind power capacity in the North and Baltic Sea, which is 6.5GW for 2020. With last year’s commissioning of BorWin 3, TenneT’s ninth offshore grid connection system in DC technology, the TSO now has a total of twelve offshore grid connections in operation (nine in DC and three in AC technology) with a total capacity of 7.1GW. But TenneT is not resting on its successes to date: The connection systems DolWin5, DolWin6, and BorWin5 are being developed and will increase the offshore transmission capacity provided by TenneT for wind farms in the German North Sea to almost 10GW by 2025. In addition, Borssele Alpha, TenneT’s first offshore connection system in AC technology in the Dutch North Sea, was installed on schedule and is now ready for operation. Borssele Beta will be completed in 2020.

Onshore, TenneT has eight transmission lines under construction in Germany, more than ever before. In the Netherlands, the 60km-long Randstad 380kV North Ring power line was put into operation, reliably supplying Europe’s most densely populated area with electricity and providing transmission capacity for green energy. At European level, the “green” COBRAcable deserves special mention, which since 2019 directly connects the Dutch and Danish markets for the first time. The German and Norwegian markets will also be directly connected by the NordLink cable, which is currently under construction. On top of this, a proof-of-concept for the North Sea Wind Power Hub has shown the technical feasibility of the concept of multiple wind power distribution hubs in the North Sea.

All these grid expansion projects are complemented by innovative solutions and intensive research to better utilise TenneT’s existing transmission system. These include vehicle-to-grid pilots, the deployment of home storage systems in grid stabilisation and digital solutions for higher grid utilisation. Another long-term innovation project is Element One, a 100MW electrolysis plant to be built in Germany to promote an integrated energy system.

TenneT presents Integrated Annual Report 2019 and Green Finance Report 2019 (picture: TenneT)

Linkup
> See TenneT press release (html)
> Visit Integrated Annual Report 2019 site (html)
> Direct access to the report download (html)
> Open Green Finance Report 2019 (pdf, 802.38kB)

See article on single page

50Hertz: More renewables, less redispatch

10.03.2020

For 50Hertz, the transmission system operator (TSO) from the north-east of Germany, the 2019 business year was successful in two respects: More renewable power than ever before was transmitted by 50Hertz. At the same time, fewer and fewer redispatch measures were required for congestion management. This of course also means that the TSCNET shareholder was able to continuously reduce its redispatch costs.

At the 50 Hertz annual media conference in the German capital of Berlin, the TSO presented the following figures: A total of around 60TWh of renewable energy was fed into the grid, mainly generated by wind and sun. This once again set a record in the 50Hertz control area, where renewable energies already cover up to 60% of the average annual electricity demand. In congestion management, 50Hertz was able to reduce the throttled energy volumes from 4TWh in 2018 to only 2.5TWh in 2019 and cut redispatch costs from €134m to €84m.

Stefan Kapferer, CEO of 50Hertz, commented on the TSO’s success: “The north-east of Germany continues to evolve into a ‘green power plant’ of the energy transition in Germany. Even with a constantly growing share of wind and solar power in the grid, we keep the costs under control. With regard to the time after the exit from coal- and lignite-fired generation, we stand for the security of the power system and create the necessary preconditions.”

50Hertz keeps on creating the technical conditions for future success and is making good progress in grid optimisation, reinforcement and expansion. Last year, the offshore grid connection Ostwind 1 was officially commissioned. In addition, 50Hertz lines and substations have been reinforced. To improve the prognosis of grid losses, artificial intelligence (AI) is used in the 50Hertz grid. All this is not possible without sustained financial commitment. Thanks to consistently good business performance – annual result 2019: €178m (2018: €238m) – the TSO will significantly increase its infrastructure investments: In the period 2020 to 2024, investments will grow by €1.1bn to €4.2bn compared to the time span 2015 to 2019.

50Hertz presents impressive figures for 2019 and announces increased investments (picture of Kerstin Maria Rippel, Head of Communications & Public Affairs at 50Hertz, 50Hertz CEO Stefan Kapferer, 50Hertz CFO Marco Nix, and Chris Peeters, CEO of Elia Group: 50Hertz / Jan Pauls)

See article on single page

Deep Dig-It trencher at work for TenneT

09.03.2020

The Hollandse Kust (South) offshore wind area in the Dutch North Sea is located 22 kilometres off the coast of the Dutch province of Zuid-Holland. TSCNET shareholder TenneT is responsible for connecting the wind farms under construction there via two corresponding offshore platforms to the onshore high-voltage substation in the industry and port area of Maasvlakte, from where the green electricity is transmitted further to the Randstad 380kV South Ring power line in the Dutch Randstad region, the most densely populated area in Europe, and further.

But there is a major challenge to be met by the Dutch-German transmission system operator (TSO): On the first ten kilometres of the offshore route, the four submarine cables to be laid are crossing the entrance to Europe’s busiest cargo port, the port of Rotterdam. To pass through the busy Rotterdam-Maasmond shipping lane, the cables here must be buried more than 5 metres deep into the seabed. For this specific job, the Dutch maritime contracting company Van Oord designed and built the Deep Dig-It trencher, a gigantic remote-controlled trencher.

Last Friday, final tests were carried out in the Aleksiahaven of Maasvlakte in preparation for the actual laying of the submarine cables in July. The innovative device is a so-called Tracked Remotely Operated Vehicle, which drives unmanned over the seabed, creates a deep trench for the cables, inserts the cables and closes the trench again. The Deep Dig-It is the largest and most powerful machine in its class. The trencher weighs 125 tonnes, is more than 17 metres long, well over 8 metres high and 11 metres wide. This makes it possible to bury cables in very hard ground, while the burial depth that can be achieved with the Deep Dig-It is well over 5 metres.

TenneT employs the powerful Deep Dig-It trencher to connect the Hollandse Kust (South) wind farms to the onshore grid (picture: Van Oord nv)

Linkup
> See TenneT press release (html)

See article on single page

BorWin3 operation handed over to TenneT

14.02.2020

The offshore grid connection BorWin3 in the German Bight near the island of Borkum has been operational since August 2019. The twelfth offshore grid connection project of TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO), extends TenneT’s transmission capacity for offshore wind farms in the German North Sea by a further 900MW, so that the total capacity already amounts to 7.132GW – and since the German government’s expansion targets for wind energy in the North Sea by 2020 are only 6.5GW, the TSO has clearly exceeded them.

After several weeks of trial operation, BorWin3 has now been handed over to TenneT by the general contractors. The consortium of Siemens and Petrofac was responsible for the construction, transport, installation and commissioning of the two BorWin3 converters (offshore and onshore). The transfer of operations represents a further major contribution to the energy transition in Germany and Europe.

At the same time, TenneT is pursuing ambitious goals for its Dutch offshore projects. The TSO is planning on a large scale, as the Dutch government has set a target in its “Offshore Wind Roadmap 2030” to reach a cumulative offshore wind capacity of 11.5GW by 2030, so that 40% of the Dutch electricity demand will then come from offshore wind farms. In the IJmuiden Ver wind energy area, off the coast of the region of North Holland, the company intends to implement two 2GW offshore grid connections to complement the eight 0.7GW AC grid connections already planned in the Dutch North Sea. As there is currently no 2GW grid connection, a new platform design and a high-voltage direct current (HVDC) transmission system that enables increased power transmission are required.

Furthermore, given the long distance to the coast and the size of the IJmuiden Ver wind energy area, a 2GW HVDC solution based on 525kV seems to be the most economically solution. It requires only one cable system per 2GW, which limits the impact on the environment and surroundings. The technology is by no means fundamentally new to TenneT. The TSO can draw on its extensive HVDC experience with offshore grid connections in Germany and with interconnectors. TenneT also uses the 525kV level for NordLink, the new offshore connection between Germany and Norway.

To implement such an innovative DC system, TenneT has initiated the design phase with five HVDC suppliers based on an innovation partnership. These suppliers will develop the advanced 2GW-525kV HVDC solution based on the criteria defined by the company and the technical capabilities of the partners.

The operation of BorWin3 was handed over to TenneT (picture of the offshore converter platform BorWin gamma: TenneT)

Linkup
> See TenneT press release on BorWin3, in German (html)
> See TenneT press release on Dutch 2GW plans (html)
> Watch BorWin3 project movie, in German (YouTube)

See article on single page

Ostwind 1 in regular operation

14.02.2020

In April 2019, the Arkona wind farm in the “Westlich Adlergrund” cluster in the Baltic Sea near the German island of Rügen was commisioned, giving the go-ahead for full operation of the Ostwind 1 grid connection of TSCNET shareholder 50Hertz, the transmission system operator (TSO) from northeast Germany. Ostwind 1 is the first grid connection in the Baltic Sea with 220kV three-phase current technology, which enables a higher transmission capacity.

Now Ostwind 1 has gone into regular operation and the two connected wind farms, besides Arkona also the Viking wind farm, have been successfully connected to the onshore grid on schedule. But 50Hertz considers this success no cause to rest on its laurels, for the expansion of offshore wind energy must continue if the energy transition is to succeed. This is why the TSO has already made good progress with the follow-up project Ostwind 2.

For instance, 50Hertz has long since begun preparations for the construction of three submarine cable systems for the Ostwind 2 project. For the land section, the 12 nautical mile zone of Mecklenburg-Western Pomerania and an approximately 5km-long section in the exclusive economic zone, the building permits have already been issued. 50Hertz has set up a new website for the Ostwind 2 project, where further information can be found.

Ostwind 1 grid connection of 50Hertz in the Baltic Sea has gone into regular operation (picture of Arkona wind farm: Ein Dahmer / CC BY-SA 4.0)

Linkup
> See 50Hertz press release (html)
> Visit Ostwind 2 project website (html)

See article on single page

Onshore converter for the Combined Grid Solution

31.01.2020

The Danish-German Combined Grid Solution (CGS) in the Baltic Sea is the world’s first offshore interconnector to use national grid connections of offshore wind farms to link the transmission systems of two countries. For this purpose, submarine cables were laid between the offshore transformer stations of the German wind farm Baltic 2 and the Kriegers Flak wind farm in the Danish part of the Baltic Sea. The CGS is a joint project of TSCNET shareholder 50Hertz, one of the four German transmission system operators (TSOs), and TSCNET customer Energinet, the TSO from Denmark.

The Bentwisch substation near the Baltic port city of Rostock houses the German onshore converters for the CGS. Here 50Hertz has installed a double converter system including a back-to-back converter. This is essential for balancing the asynchronous transmission systems of Germany and Eastern Denmark: The AC from the Nordic synchronous area is converted into DC and directly back into AC, now adapted to the European synchronous area.

50Hertz has now successively energised and commissioned all converter components in Bentwisch. The new equipment and further extensions of the substation had to be individually synchronised with the control technology in a series of individual testing and commissioning steps. The operational readiness of the double converter system in Bentwisch marks another important milestone on the way to the commissioning of the entire CGS.

The German onshore converter for the Danish-German offshore interconnector Combined Grid Solution has been commissioned by 50Hertz (picture: Jan Pauls / 50Hertz)

Linkup
> See 50Hertz project news (html)

See article on single page

European wind energy record shares in 2019

14.01.2020

Not much time has passed in the new year, but the German-based International Economic Forum for Renewable Energies (Internationales Wirtschaftsforum Regenerative Energien/IWR) has already evaluated the electricity data for 2019 provided by the European Network of Transmission System Operators for Electricity (ENTSO-E) on behalf of the member transmission system operators (TSOs). According to the IWR, the total share of all renewable energies in the energy mix has continued to rise. Wind and solar power generation reached new all-time highs (almost 510TWh), while electricity production from hydropower remained comparatively low due to the long dry phase in 2019.

In the EU, wind energy was the most important regenerative energy source in 2019 with around 392TWh (2018: 349TWh). The statistical analysis of the IWR coincides with the figures which the Dutch-German TSO TenneT has just published for the feed-in of electricity from German North Sea wind farms. The TSCNET shareholder in 2019 has increased the offshore wind energy connection capacity of its twelve German offshore grid connection systems currently in operation to 7,132MW. For one thing, this means that the “wind harvest” record figures exceed the previous year by around 21%. Secondly, the TSO has already now achieved and even significantly exceeded the German federal government’s targets for the sustainable expansion of offshore wind energy. The government’s target for the North Sea and Baltic Sea together by 2020 is 6.5GW in total.

Expressed in absolute figures, the wind energy transmitted by TenneT from the North Sea reached a new record of 20.21TWh in 2019 (16.75TWh in 2018). TenneT managing director Tim Meyerjürgens comments on the progress: “We are pleased that we have already achieved the goal set by the federal government ahead of schedule and with the three other offshore grid connections currently being implemented, we will be capable of delivering 10,000MW of transmission capacity from the North Sea in 2025 in Germany alone.”

European figures for wind energy in 2019 are at a record high, as is the German offshore grid connection capacity of TenneT

Linkup
> See TenneT press release (html)
> See IWR press release, in German (html)

See article on single page

TenneT participates in Ocean Renewable Energy Action Coalition

13.01.2020

The Dutch-German transmission system operator (TSO) TenneT is continuously increasing the amount of sea-generated wind energy transmitted ashore. The TSCNET shareholder is also the initiator of the pioneering North Sea Wind Power Hub concept that combines generation, storage and transmission of wind energy with a multinational interconnection of North Sea riparian states. Now TenneT is also participating in the just founded international Ocean Renewable Energy Action Coalition to promote the sustainable use of marine renewable energy and reduce the harmful effects of climate change.

Not only wind power but also floating solar, tidal and wave power count among the maritime renewable energy potentials. According to a report by the High-Level Panel for a Sustainable Ocean Economy, together they could provide almost 10% of the annual greenhouse gas emission reductions needed by 2050 to keep global temperatures below 1.5°C above pre-industrial levels. However, offshore wind energy is likely to make up the largest part of this climate protection potential.

The Action Coalition was established in response to the High-Level Panel’s September 2019 call for ocean-related climate protection activities and brings together civil society, intergovernmental institutions and industry. It will represent the offshore wind sector in the global dialogue on climate change and be led by the Scandinavian power companies Ørsted and Equinor. The total of eleven partners will develop a vision for 2050, highlighting the actions to be taken to sustainably expand offshore wind energy, thereby contributing to the UN’s sustainable development goals and global decarbonisation targets. First results will be announced at the UN Ocean Conference in Lisbon in June 2020.

TenneT is part of the Ocean Renewable Energy Action Coalition to promote the sustainable use of renewable marine energy (picture: TenneT)

See article on single page

New 50Hertz CEO takes up duties

03.12.2019

On 1 December, Stefan Kapferer took office as the new chairman of the executive board of TSCNET shareholder 50Hertz, one of the four German transmission system operators (TSOs). Until the end of October 2019, Kapferer headed the German Energy and Water Association (Bundesverband der Energie- und Wasserwirtschaft – BDEW). Kapferer succeeds interim CEO Dr. Frank Golletz, CTO of 50Hertz, who took over the additional duties after former CEO Boris Schucht had left the company in March 2019.

At a purpose-arranged press conference on 3 December in the German capital Berlin, Stefan Kapferer acknowledged the appeal and diversity of his new task. “The next phase of the realisation of the energy transition is an even greater challenge in terms of entrepreneurship and the European side of things. TSOs play an essential role here,” explained Kapferer. The main issues to be dealt with by 50Hertz are the German coal phase-out, following the current nuclear phase-out, the national legislative climate specifications and the grid extension which is essential for all these measures. For a Baltic Sea riparian TSO, it is particularly important to set the right course for the development of offshore wind energy.

Chris Peeters, head of the 50Hertz supervisory board, highlighted Kapferer’s wealth of political and international experience as former German State Secretary and Deputy Secretary General of the OECD and concluded: “I am convinced that Kapferer’s skills combined with the technical know-how of our staff will result in a great future for 50Hertz. Together we work for our goal: a successful energy transition.”

Stefan Kapferer is in office as new CEO of 50Hertz (picture: 50Hertz / Jan Pauls)

Linkup
> See 50Hertz press release (html)

See article on single page