€215m for green connection capacity

11.10.2019

The Dutch-German transmission system operator (TSO) TenneT plans to invest a further €215m to connect two GW of green electricity from solar and wind farms in the north of the Netherlands to the grid. The infrastructural measures include the construction of two new 380/110kV high-voltage substations in the provinces of Groningen and Drenthe. In addition, the TSCNET shareholder intends to provide extra capacity at nine existing 110kV substations in the northern Netherlands.

One GW corresponds roughly to the output of 3.5 million solar modules or 200 wind turbines. The additional capacity planned by the TSO is therefore considerable, but according to Ben Voorhorst, COO of the TSO, as many solar and wind farm transmission requests as possible should be complied with. Already now TenneT operates projects in the northern Netherlands with a volume of more than €1bn. This level of investment is now being further increased, with the TSO focusing strongly on the sustainability and efficiency of the investments. “The better the capacity expansions of electricity grids are actually utilised, the better the consumer’s money is spent,” explains Voorhorst.

TenneT invests €215m in the connection of renewable energies in the northern Netherlands (picture: TenneT)

Linkup
> See TenneT press release (html)

See article on single page

Borssele Alpha ready to operate

05.09.2019

Just one month ago, TSCNET shareholder TenneT fully implemented BorWin3 in the German Bight, the twelfth offshore grid connection project of the Dutch-German transmission system operator (TSO). Now there is once again good news for the energy transition, this time from the Dutch North Sea: Borssele Alpha, TenneT’s first and largest connection system for wind farms in Dutch territorial waters, is ready for operation – right on schedule and within budget. From 2020 on, Borssele Alpha will supply the green electricity from the offshore wind farms Borssele I and II ashore.

The two Borssele wind farms will have a capacity of around 700MW. The Borssele Alpha grid connection will transmit the electricity to the substation near the town of Borssele in the Dutch province of Zeeland, where TenneT has built a new transformer station next to the existing station. The Borssele grid connection is TenneT’s first Dutch major project under the National Energy Agreement for offshore wind farms and fully complies with the conditions set out in the Dutch government’s Offshore Wind Energy Development Framework.

According to the Energy Agreement, TenneT will have installed 3,500MW of grid connections for offshore wind farms by the end of 2023. The next project is Borssele Beta, followed by Hollandse Kust (zuid) Alpha and Beta and Hollandse Kust (noord). TenneT’s standardised procedure for offshore connections will make it possible to complete these projects more efficiently, quickly and economically. In line with the Dutch Follow-up Roadmap for Offshore Wind Energy, a further 6,100MW of offshore wind energy will be realised between 2024 and 2030.

The Borssele Alpha offshore grid connection of TenneT is operational (picture: Screenshot taken from the Borssele video)

Linkup
> See TenneT press release (html)
> Watch TenneT video “Opening Borssele Trailer Master” (YouTube)

See article on single page

COBRAcable market launch on 7 September

02.09.2019

After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule. The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO.

The high-voltage DC cable with a length of about 325km has a capacity of 700MW. The Netherlands can import more sustainable electricity from Denmark through COBRAcable, mainly wind energy. In addition, the cable provides Dutch capacity on a structural basis for the Danish electricity grid, thus ensuring security of supply in Denmark, which of course also works the other way round. Moreover, the cable connection is designed in such a way that an offshore wind farm can be connected at a later date, so that COBRAcable contributes to a sustainable European energy landscape.

The COBRAcable interconnector of Energinet and Tennet is available to the market from 7 September (picture: screenshot taken from TenneT-video “First pile COBRAcable”, YouTube)

Linkup
> See TenneT press release (html)

See article on single page

TenneT on track for the energy transition

31.07.2019

Highly satisfactory business results and maintenance of the high level of 99.99% security of supply, are hallmarks of the half year report of the Dutch-German TSCNET shareholder Tennet. The latter is a growing challenge for the transmission system operator (TSO) because of the increased feed-in of volatile renewable energy. But above all, the report illustrates the commitment of the TSO to the European energy transition.

To take further steps in shaping the energy system of the future, TenneT has launched a series of strategic initiatives and partnerships to join forces across sectors. TenneT is participating in a German power-to-gas pilot project and is working together with regional grid operators and market partners on smart solutions to optimise the use of existing electricity infrastructure. The TSO is also involved in blockchain pilots to create flexibility for balancing the power system from decentralised sources.

TenneT has further strengthened its position as a leading offshore TSO. In Germany, TenneT has awarded DolWin 5, the 14th offshore grid connection. TenneT will increase its current offshore transmission capacity from 6,232MW in the German North Sea to almost 9GW by 2024. In the Netherlands, too, the development of the offshore grid with the Borssele Alpha and Beta projects is on schedule. TenneT intends to provide a total of 10.6GW of connection capacity for Dutch offshore wind farms by 2030. The TSO is also carrying out several onshore projects to ensure the transport of the growing amount of green electricity and thus security of supply in its control areas. Important interconnecting projects are the NordLink cable connection, which is currently being built to directly link the German and Norwegian markets for the first time. The COBRAcable between the Netherlands and Denmark has “landed” at the Dutch shore and will go into operation this year.

These developments are complemented by solid and impressive figures: Underlying operating result (EBIT) rose from €362m (first half of 2018) to €407m in the first half of 2019. €1,094m (first half of 2018: €904m) were invested in the Dutch and German high-voltage grids (of which €612m in Germany) and a total of €1.75bn green bonds were successfully issued. Manon van Beek, CEO of TenneT, comments on the report: “We have embarked on an irreversible transition to a sustainable society and a new energy system. This requires investments, not only in new electricity connections, but also in innovations and digitalisation. We have to move to holistic energy system thinking and also work on solutions to make better use of the existing high-voltage grids. We are convinced that this is the way forward to limit social costs and at the same time maintain a very high security of supply.”

TenneT presents its half year report 2019 (picture: TenneT)

Linkup
> See TenneT press release (html)
> Open Half year report 2019 (pdf, 803kb)

See article on single page

TenneT’s “sea harvest” increases

15.07.2019

9.51TWh – this is the considerable total amount of offshore wind power that TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO), transmitted from sea to land in the first half of 2019. This means that the first half of 2018 (8.17TWh) will be exceeded by a whopping 16%, while on the German market offshore wind energy accounts for a strong 15% of total wind energy generation. At the same time, the cost efficiency of new offshore grid connection systems has further improved in recent months through the standardisation of TenneT’s offshore grid connection systems and the combined expertise of TenneT as a leading TSO at sea.

With the connections currently planned and under construction, TenneT will increase offshore transmission capacity in the German North Sea to almost 9GW by 2024. However, current efforts in Europe will not be sufficient to achieve the climate targets of the Paris Agreement. TenneT therefore calls for a stronger expansion of offshore wind energy in Europe to create a low carbon energy future. TenneT COO Tim Meyerjürgens refers to international studies and scenarios that indicate that “an accelerated and large-scale roll-out is necessary”.

In this context, Meyerjürgens also points to the North Sea Wind Power Hub (NSWPH) concept, for which a positive feasibility study has just been carried out. The North Sea has great potential for offshore wind power, and the NSWPH consortium’s approach could result in 180GW of offshore wind power by 2045. Meyerjürgens explains: “A future internationally coordinated approach could implement the connection and integration of a roll-out of large-scale offshore wind energy more effectively and at considerably lower costs of up to 30% than with continued individual national planning.”

Offshore wind energy transmission by TenneT rose to 9.51TWh in the first half of 2019 (picture of SylWin Alpha converter platform: Tennet)

Linkup
> See TenneT press release with detailed facts and figures (html)

See article on single page

TSO offshore connections are most cost-effective

26.06.2019

In most European countries with offshore wind farms, the respective transmission system operators (TSOs) are responsible for connecting these offshore facilities to the onshore grid, which they also operate. The TSCNET shareholders affected by this arrangement include the north-eastern German TSO 50Hertz, the Danish TSO Energinet and the Dutch-German TSO TenneT. But obviously this handling is not the only one possible. In the UK, for instance, the developer of the particular offshore wind farm is also responsible for its grid connection.

In concrete terms, this means that in the UK the offshore grid connection after its completion is sold to commercial investors and a so-called OFTO (Offshore Transport Owner) is established. But which model, the TSO model or the OFTO model, causes the lowest costs for consumers and thus for society?

The internationally accredited registrar and the world’s largest classification society, DNV GL, has investigated this question in more detail. The main outcomes of this study are that in the OFTO system the costs for the development of offshore connections are significantly higher than in Denmark and the Netherlands. In contrast, the Levelised Cost of Energy (LCOE) of the Dutch and Danish offshore connections is significantly lower. The LCOE assesses the average total cost of constructing and operating an energy generating asset over its lifetime divided by its total energy output over that lifetime.

DNV GL has documented lower costs for the TSO connection of offshore wind farms than for the OFTO solution (illustration of Borssele Alpha: TenneT)

Linkup
> See TenneT news release (html)
> Open DNV-GL report (pdf, 453.83kb)

See article on single page

Imminent test operation for COBRAcable

24.06.2019

COBRAcable, the first direct interconnection between the electricity markets of Denmark and the Netherlands, is a joint project of the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO. Since spring, the partner TSOs have been preparing the commercial operation of COBRAcable. TenneT and Energinet have now launched an Urgent Market Messages (UMM) site for the commissioning of COBRAcable, which is scheduled to take place between 3 July 2019 and 6 September 2019.

A total of around 30 individual tests with different energy charges in the respective transport directions are planned. It is expected that the full capacity of COBRAcable will be available for the day ahead and intraday markets from 7 September. TenneT and Energinet then will offer financial transmission rights on COBRAcable at monthly and annual auctions. The first auction is expected to take place after a full month of stable operation, so probably the auction for November 2019, which will be held in October.

By promoting the exchange of surplus wind energy, COBRAcable will improve the cohesion of the European transmission system and the integration of the electricity market. It will also make a sustainable contribution to the low carbon energy future by allowing future offshore wind farms in the North Sea to be hooked up to the DC interconnector.

Energinet and Tennet will carry out individual tests of COBRAcable as of 3 July (picture: screenshot taken from TenneT video “COBRAcable Cable Pull Fano Denmark Film”, YouTube)

Linkup
> See Energinet press release (html)
> Visit REMIT UMM site (html)

See article on single page

Eco-friendly substation maintenance

13.05.2019

In total, TSCNET shareholder TenneT operates 462 high-voltage substations in the Dutch and German control areas of the binational transmission system operator (TSO). The operation of a high-voltage grid inevitably involves interference with ecosystems, but TenneT is investigating how to minimise and compensate for this. For this reason, the TSO has carried out a pilot project on biodiversity at three substations in the Netherlands.

The results of the pilot are impressive: The nature-friendly maintenance of the three facilities has preserved up to 72 percent of their insect populations. The respective measures to increase biodiversity can easily be replicated. Local seed mixtures were sown, and greens were mown in a meandering manner. Based on these encouraging results, TenneT will promote biodiversity at all of its 462 substations.

TenneT intends to establish biodiversity-friendly management as the corporate standard by 2025. This commitment to biodiversity is part of the TSO’s Corporate Social Responsibility approach for 2025 and reflects the company’s ambition to play a leading role in the energy transition as a “Green Grid Operator”. Ben Voorhorst, member of TenneT’s Executive Board, explains: “With our high voltage connections and stations, in addition to transporting green electricity, we can also contribute to the conservation of nature in another way.”

TenneT is introducing biodiversity-friendly substation maintenance (picture: kie-ker/Pixabay)

Linkup
> See TenneT press release (html)

See article on single page

First Borssele cable ashore

17.04.2019

Last weekend, the first submarine cable from the Borssele Alpha transformer platform landed on the Dutch coast, marking a significant progress in connecting the Borssele offshore wind farm area in the southwest part of the Dutch North Sea to the onshore high-voltage grid of TSCNET shareholder TenneT. The Borssele grid connection is the first large-scale project of the Dutch-German transmission system operator (TSO) carried out under the Dutch National Energy Agreement for offshore wind farms.

The last section of the cable laying was quite critical due to the crossing of a ferry route, but during the closure of the shipping traffic everything went according to plan. After the landing of the submarine cable, its installation was continued ashore up to the newly constructed onshore transformer substation. In the coming weeks preparations will be made to connect the second submarine cable for the Borssele Alpha project to the transformer station.

The first submarine cable of the Borssele grid connection of TenneT has reached the coast (picture: TenneT)

Linkup
> See TenneT press release (html)

See article on single page

Record-setting offshore connection

09.04.2019

The IJmuiden Ver offshore wind farm project in the Dutch sector of the North Sea will be equipped with two onshore connections from 2024 to 2030. TSCNET shareholder TenneT, the Dutch-German transmission system operator (TSO), has announced to link the 6.1GW of the new offshore wind farms to the Dutch high-voltage grid via two 525kV DC cables with a capacity of 2GW – this will be the highest in the world. As a result of the increased capacity, only two instead of six cables will be required, resulting in lower costs, as well as less space requirements and environmental impact.

A total of four converter stations are required for the DC transmission, which prevents transport losses: two offshore converter platforms for converting the wind-generated AC into DC and two onshore converters for the reconversion. The 2GW connections are possible due to TenneT’s unique experience with HVDC grid connections in Germany, where TenneT will connect offshore wind farms with DC technology on a large scale. The TSO also uses the 525kV high voltage level for NordLink, the new international connection between Germany and Norway, as well as for the German onshore projects SuedLink and SuedOstlink.

TenneT has ambitious offshore plans, since the TSO has been commissioned by the Dutch government to connect a total of 9.6GW offshore capacity, of which 5.6GW will be realised with AC connections and 4GW with innovative DC connections. Together with the offshore wind farms already in operation, the offshore wind energy capacity is expected to reach 10.6GW in the Netherlands in 2030. Because of the considerable total capacity of IJmuiden Ver, the associated onshore connection is a core component of TenneT’s offshore grid development in the Netherlands.

Manon van Beek, CEO of TenneT, comments on the IJmuiden Ver project: “We are making an important contribution to accelerating the energy transition. Based on our experience with innovative technology in Germany, we can now help to realise the Dutch ambitions for the development of offshore wind energy with fewer cables, fewer platforms and less spatial impact and nuisance to the environment, both at sea and on land.”

TenneT connects Dutch offshore wind farm with a record capacity of 2GW (picture: TenneT , artist’s impression)

Linkup
> See TenneT press release, in Dutch (html)
> Open artist’s impression video (TenneT, YouTube)

See article on single page