Delay for Interim Coupling

11.09.2020

To introduce single day-ahead coupling in a total of 23 European countries, the so-called 4M Market Coupling Countries (4M MC) – Czech Republic, Hungary, Romania, and Slovakia – are to be connected to the Europe-wide Multi Regional Coupling (MRC) of the electricity market. The initiative to implement the MRC extension is the DE-AT-PL-4M project, also referred to as “Interim Coupling Project”. It aims to establish implicit capacity allocation based on Net Transfer Capacity (NTC) at six borders: PL-DE, PL-CZ, PL-SK, CZ-DE, CZ-AT, and HU-AT. The TSCNET shareholders 50Hertz, APG, ČEPS, MAVIR, PSE, SEPS, TenneT, and Transelectrica – transmission system operators (TSOs) from Austria, Czechia, Germany, Hungary, Poland, Romania, and Slovakia – participate in Interim Coupling.

After the project had completed the design phase and entered the implementation phase at the end of 2019, Interim Coupling was actually supposed to start in September 2020. The TSOs and Nominated Electricity Market Operators (NEMOs) involved have now announced that the kick-off must be postponed. This is due to several project parties experiencing local implementation bottlenecks in the first quarter of 2020 because of interrelations between ongoing parallel projects. This led to a delay of several months in the implementation activities for Interim Coupling. National regulatory authorities have asked the European Commission to provide guidance on how to proceed with this project. Market players will be informed as soon as possible about the next steps.

The start of the AT-PL-4M MC project has been postponed

Linkup
> See MAVIR press release, html
> See PSE press release, html
> See SEPS press release, html
> Open AT-PL-4M MC information paper provided by Transelectrica (pdf, 262.12kB)

See article on single page

Paper on MRC extension

26.03.2020

The so-called 4M Market Coupling Countries (4M MC) – the Czech Republic, Hungary, Romania and Slovakia – are to be connected to the Europe-wide Multi Regional Coupling (MRC) of the electricity market. This will introduce Single Day-Ahead Coupling across 23 European countries. The initiative to implement the MRC expansion is the DE-AT-PL-4M MC Project, also known as “Interim Coupling Project”. The relevant transmission system operators (TSOs) from Austria, Czechia, Germany, Hungary, Poland, Romania and Slovakia – the TSCNET shareholders 50Hertz, APG, ČEPS, MAVIR, PSE, SEPS, TenneT, and Transelectrica – are part of the project consortium.

The AT-PL-4M MC Project establishes implicit capacity allocation based on Net Transfer Capacity (NTC) at six borders (PL-DE, PL-CZ, PL-SK, CZ-DE, CZ-AT, HU-AT). The Nominated Electricity Market Operators (NEMOs) and TSOs participating in the DE-AT-PL-4M MC Project now have published an information paper for market participants containing key information on the project in a question and answer format. This information includes the main expected changes for the market, the planned communication methods with market participants and a high-level technical description of the market design to be implemented by the project.

The partners of the AT-PL-4M MC Project for integrating Czechia, Hungary, Romania and Slovakia into MRC have published an information paper

Linkup
> Open AT-PL-4M MC information paper provided by MAVIR (pdf, 732.98kB)

See article on single page

Multi Regional Coupling expanded by the end of 2020

17.12.2019

The Multi Regional Coupling (MRC) of the European electricity market is to be substantially enhanced by connecting the so-called 4M Market Coupling Countries (4M MC), i.e. the Czech Republic, Hungary, Romania and Slovakia, to the Europe-wide MRC. This will establish Single Day-Ahead Coupling across 23 European countries.

In preparation for this market integration, the so-called Interim Coupling Project (DE-AT-PL-4M MC Project) was launched. It has now completed the design phase and is entering the implementation phase. This provides the Nominated Electricity Market Operators (NEMOs) and transmission system operators (TSOs) from Austria (APG), Germany (50Hertz, Amprion, TenneT, and TransnetBW), Poland (PSE) and the 4M MC countries (ČEPS, MAVIR, Transelectrica and SEPS) with a sound basis for announcing the MRC inclusion for the third quarter of 2020.

The AT-PL-4M MC Project introduces implicit capacity allocation based on Net Transfer Capacity (NTC) at six borders (PL-DE, PL-CZ, PL-SK, CZ-DE, CZ-AT, HU-AT). The competent National Regulatory Authorities (NRAs) welcome the progress made and the synergies from the project, which will facilitate the introduction of Flow-Based Market Coupling in the Core Capacity Calculation Region (Core CCR), which is the ultimate target.

The AT-PL-4M MC project for integrating Czechia, Hungary, Romania and Slovakia into MRC has entered the implementation phase.

Linkup
> See PSE press release (html)
> See SEPS press release (html)
> Open joint press release (pdf, 216.14kB)

See article on single page

High-Level Market Design finalised

11.06.2019

It was only at the end of 2018 that the national regulatory authorities of Austria, Germany, Poland and the so-called 4MMC countries (Czechia, Hungary, Romania, and Slovakia) requested the initiation of the interim project for an NTC-based market coupling (“Net Transfer Capacities”) between these countries. The parties involved in the DE-AT-PL-4MMC (“Interim Coupling”) project have completed the High-Level Market Design to be implemented and the national regulatory authorities have confirmed their support for the continuation of the project. This involves a total of eight TSOs that are shareholders and customers of TSCNET Services: 50Hertz (Germany), APG (Austria), ČEPS (Czechia), MAVIR (Hungary), PSE (Poland), SEPS (Slovakia), TenneT (Germany), and Transelectrica (Romania).

The project aims to couple 4MMC and Poland as well as Multi-Regional Coupling (MRC) through the introduction of NTC-based implicit allocation on six borders (PL-DE, PL-CZ, PL-SK, CZ-DE, CZ-AT, HU-AT) and the implementation of a Single Day Ahead Coupling (SDAC). The project envisages a step-by-step transition at the above-mentioned boundaries from the current NTC-based explicit allocation to the flow-based implicit allocation to be implemented in the framework of the CoreFlow-Based Market Coupling Projectas target solution required by regulation. The Interim Coupling significantly contributes to the regional market integration and brings benefits to the market. The current planning envisages the go-live of the interim coupling for the second quarter of 2020.

The parties involved in the DE-AT-PL-4MMC project have completed the High-Level Market Design