Ernen-Ulrichen 380kV line in operation

21.10.2019

With the erection of the last of a total of 57 pylons, the new extra-high voltage line between the Ernen and Ulrichen substations in the Swiss canton of Valais has now been completed. The 30-kilometre section is part of the 380kV Mörel-Ulrichen line project of TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO). The line upgrade in the Rhône Valley is vital for the future of Switzerland’s energy supply: In order to fully transfer the hydropower generated in the Valais to the urban areas of Switzerland, the lines of the south-western canton must be connected to the supra-regional 380kV transmission grid, particularly in view of the commissioning of the new Nant de Drance pumped storage power station, scheduled for 2020.

The existing 220kV overhead line between Ernen and Ulrichen is already disconnected. Its 177 pylons will be dismantled from spring 2020 and the former pylon locations will be recultivated. Swissgrid is additionally carrying out nature conservation projects of national importance in the vicinity of the new line. Also starting next year, the Swiss TSO will continue its Valais upgrade project with the new construction of the next section between Ernen and Mörel-Filet, which is expected to be commissioned as 380kV line by the end of 2022.

Swissgrid has commissioned the new 380kV line between Ernen-Ulrichen (picture: Swissgrid)

Linkup
> See Swissgrid news release, in German (html)

See article on single page

50 new pylons for the Pradella-La Punt line

19.09.2019

The extra-high voltage line in the Swiss Engadine between Pradella/Scuol and La Punt represents a bottleneck in the Swiss and the European transmission grid. To remedy this shortcoming, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), began upgrading the 380kV line to 2 x 380kV in October 2017. This will increase import capacity from the north, strengthen interconnections with Austria and Italy and facilitate the transport of hydropower in the canton of Grisons. The project also improves security of supply in Switzerland and is part of the “Strategic Grid 2025”, Swissgrid’s ambitious modernisation and expansion plan.

Basically, the upgrade means that Swissgrid will attach a second 380kV line to the pylons, which are originally fitted with only one line on one side. Over the past two years, the TSO has reinforced the mast foundations between Pradella and La Punt and will complete this work in autumn. But Swissgrid has also examined the static of the pylons and discovered that some of them have insufficient load capacity for the second circuit. For safety reasons, it was thus decided to replace 50 of altogether 127 masts instead of reinforcing them. This change has no impact on the routing, but on the schedule: The commissioning of the upgraded line will be delayed by at least one year and is now planned for 2022.

Swissgrid has to erect 50 new pylons for the Pradella-La Punt line (picture: Swissgrid)

Linkup
> See Swissgrid news release (html)

See article on single page

New 380kV line in Valais

17.04.2019

The complete transmission of hydroelectric power generated in the Swiss Canton of Valais to the country’s urban areas is essential for the future of Switzerland’s energy supply: Without the connection of the Valais transmission lines to the 380kV grid, only around two-thirds of Valais hydropower can be transmitted as soon as the new Nant de Drance pumped storage plant goes into operation. That is why increasing the voltage of the line between the Chippis and Mörel substations in the Rhone valley from 220 to 380kV is an important part of the “Strategic Grid 2025”, the grid modernisation and expansion plan of TSCNET shareholder Swissgrid, the Swiss transmission grid operator (TSO).

Swissgrid is planning the new construction of a 380kV overhead line with a length of around 44 kilometres, which will bypass and relieve settlement areas as far as possible. The existing 220kV line will be dismantled after the new line is commissioned. As with every grid project, Swissgrid has evaluated both cable and overhead line variants for Chippis-Mörel, with the result that underground installation would not only be very costly and time-consuming but would also not generate any significant added value for the natural landscape.

At the end of March 2019, Swissgrid submitted the planning approval procedure to the Swiss Federal Inspectorate for Heavy Current Installations (Eidgenössisches Starkstrominspektorat – ESTI) and also engages in dialogue with the population, the municipalities, the authorities and associations. The TSO’s current planning foresees commissioning of the line in 2025, but in the event of objections and legal proceedings, initial operation may be delayed by several years.

Swissgrid will build a new 380kv overhead line between Chippis and Mörel in Valais (picture: Swissgrid)

Linkup
> See Swissgrid media release, in German (html)

See article on single page

Official opening of substation in Ticino

01.10.2018

The commissioning of the modernised Avegno substation in the district of Vallemaggia in the Swiss canton of Ticino is a landmark achievement for TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO): “Since Swissgrid took over the Swiss transmission grid in 2013, it has been the first substation project to be fully implemented by the national grid company,” explains Maurice Dierick, Head of Grid at Swissgrid.

The Avegno substation is an important hub of the Swiss transmission network, both regionally and nationally. In addition, it connects the Verbano hydropower plant to the national extra-high voltage grid. Construction work at Avegno began in October 2016 and will be completed by the end of November with the dismantling of the old 220kV open air switchgear. Already in April 2018, the new gas-insulated switchgear (GIS) was connected to the grid. All in all, Swissgrid has invested CHF17m (almost €15m) in the modernisation of Avegno.

Swissgrid has opened the new Avegno substation, equipped with a gas-insulated switchgear (picture: Swissgrid)

Linkup
> See Swissgrid media release, in German (html)

See article on single page

Substation upgrade in the Swiss Espace Mittelland

16.05.2018

The Innertkirchen substation in the Swiss canton of Bern is an important hub of the national transmission system. As the old 220kV open air switchgear at Innertkirchen is somewhat outdated, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), replaces it with a 380kV gas-insulated switchgear (GIS). The substation modernisation is not only important for the regional long-term security of electricity supply, but also for ensuring the transmission of green energy from hydropower plants in the cantons of Bern and Valais to the centres of the Mittelland.

The conversion work started with a symbolic turn of the sod on 15 May. Since the building for the new GIS will be erected next to the existing outdoor switchgear, the operation of the substation can be fully maintained during the construction period. Investments for the entire project amount to around CHF33m, and commissioning of the new facility is scheduled for mid-2021.

> See Swissgrid media release, in German (html)

Picture: Swissgrid

See article on single page

Carinthian transformer connected to the grid

27.04.2018

The substation in Obersielach in the southernmost Austrian state of Carinthia is an essential component of the nationwide modernisation process, with which TSCNET shareholder APG, the Austrian transmission system operator (TSO), adapts its grid to the high requirements of a sustainable energy future. Last September, a large additional 380/220kV transformer was delivered to Obersielach ‒ due to its heavy weight in three parts – and then it took six months of installation work and extensive functional testing, before the new device could finally be connected to the grid on 26 April 2018. Further upgrade measures at the substation are still pending and completion is scheduled for autumn 2019. Overall, APG is investing round €38m in the operating site.

The Obersielach substation is the most important power hub in Carinthia and one of the largest substations in Austria. The commissioning of the new transformer will not only ensure the regional long-term security of electricity supply, but also improve the use of climate-friendly wind energy by means of interconnecting the wind farms in Upper Austria with the Carinthian pumped storage power plants in Malta and Reißeck. Surplus wind power can thus be transported to these “green batteries” and stored there. If necessary, the electricity can then be retrieved again from the storage power plants. Apart from that, the five largest Carinthian hydropower plants on the river Drau feed directly into the Obersielach substation.

> See APG press release, in German (html)

Picture: Erich Varh / APG

See article on single page

New transformer in Upper Austria

05.04.2018

In order to secure the long-term security of electricity supply in the Western Mühlviertel in Upper Austria as well as to improve the supply situation in the greater Linz area, TSCNET shareholder APG, the Austrian transmission system operator (TSO), is upgrading its substation near the Jochenstein Danube hydropower plant on the Austro-German border. These modernisation measures include a new 220/110kV transformer.

In September 2017, the 280-tonne transformer was delivered by ship across the Danube to Jochenstein. After five months of assembling and extensive functional tests under high-voltage, the state-of-the-art device was finally connected to the grid at the end of March 2018. The commissioning marks the completion of all construction work at the substation, with which APG ensures that green electricity from the Jochenstein hydropower plant continues to be safely fed into the Austrian transmission system. In total, APG invested €10m in the supply security of the region.

> See APG press release, in German (html)
> See APG video with background information, in German (html)

Picture: APG / APA-Fotoservice / Hautzinger

See article on single page

Line upgrade in the Engadin Valley

24.10.2017

A symbolic cut of the spade was the starting signal for the elimination of the bottleneck within the Swiss as well as the whole European transmission system, which is the power line in the Engadin Valley between Pradella and La Punt. To enhance the existing line with a length of 49 km, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), appends an additional 380kV circuit. Swissgrid also modernises the Pradella substation by substituting the old overhead station with a 380kV gas insulated substation.

The construction projects in Engadin are part of “Strategic Grid 2025”, Swissgrid’s demanding grid modernisation and expansion plan. They will increase grid stability and supply security in Switzerland. By providing capacities for the transmission of electricity from Grisons hydropower and by reinforcing interconnections to Italy and Austria, the building measures have beyond that a considerable European dimension. Preparatory works for the line upgrade started in the summer of 2017 and the commissioning of the expanded power line is expected in autumn of 2021. The new Pradella substation will probably be connected to the grid in 2020.

> See Swissgrid media release (html)

Picture: Swissgrid

.

See article on single page

Modernisation of Pleinting substation

16.02.2017

Currently, TSC member TenneT, the Dutch-German transmission system operator (TSO), modernises several of its substations. In doing so, the TSO improves the coupling of regional electricity grids to TenneT’s trans-regional transmission system and pursues three main targets: Meeting the challenges of the energy transition, ensuring grid stability, and enhancing the supply security.

One of those upgrade projects is the substation Pleinting in Lower Bavaria, near Passau and close to the Austrian-German border. The Pleinting substation is of significance for the cross-border electricity exchange, in particular for the linking of Austrian pump storage power plants to the German grid. For this reason, also the overhead power line from Pleinting to the Austrian substation St. Peter am Hart is presently being overhauled. These reconstruction works will probably be finished by April, while the modernisation of the substation is scheduled to last til 2020.

Since transformers are the centrepiece of any substation, the upgrade of Pleinting involves a complete new set of such devices. Today a direct coupling transformer weighing 260t is arriving at Pleinting by means of heavy-duty transport. The assembly of the new machine built by GE Grid Solutions will take up to three month and two more transformers are expected to be delivered until 2018.

> See TenneT press release, in German (html)

Picture: TenneT

.

See article on single page

Approval to finish Nant de Drance connection

14.02.2017

In late 2016, the Swiss Federal Inspectorate for Heavy Current Installations (“Eidgenössisches Starkstrominspektorat”, ESTI) has approved the construction plans for the final section of the grid connection of the Nant de Drance pump storage power plant as submitted by TSC member Swissgrid, the Swiss transmission system operator (TSO). Hence, all building permits for the connection of the plant in the Swiss Canton Valais near the French border to the Swiss transmission system have been granted and the implementation of the complete project now can proceed as scheduled.

Swissgrid originally intended to realise the last 1.3km from the La Bâtiaz substation to Le Verney, the connecting point to an already existing 380kV extra-high voltage line, as overhead line. According to revised plans, the Rhône valley between La Bâtiaz and Le Verney will now be crossed by means of an underground cable laid at a depth of 25 to 30 metres. Currently, Swissgrid is elaborating the technical details of this deep cable solution. The TSO will make those details known to the public once the planning and tender procedures are completed.

> See Swissgrid press release (html)

Picture: Screenshot taken from video “Nant de Drance – Höchstspannungsnetz” (Swissgrid, YouTube)

.

See article on single page