Deep Dig-It starts work for Hollandse Kust (zuid) grid

24.09.2020

Hollandse Kust (zuid), an offshore wind area in the Dutch North Sea, is located a good 20 kilometres off the coast of the Dutch province of Zuid-Holland. The Dutch-German transmission system operator (TSO) TenneT is installing the related offshore grid to connect the new offshore wind farms in the area via two offshore platforms and submarine cables to the onshore high-voltage substation that is being built in the Maasvlakte industrial and port area. The jacket for the first of these two offshore platforms has recently been installed and the offshore connection project is now making further progress with the start of the laying of the submarine cables on 22 September.

Four 220kV AC cables with a total length of 42 kilometres each are to be installed in the seabed, of which the first two to the Alpha platform will be laid this year. The other two to the Beta platform will follow in 2021. First, the two cables were brought ashore to the planned Maasvlakte substation via direct drilling. Thereupon the TSCNET shareholder started the marine installation, with the first ten kilometres of the route from the coast at Maasvlakte being extremely challenging. Over this distance, the cables cross the entrance to the port of Rotterdam – Europe’s busiest cargo port – and thus need to be buried more than 5.5 metres deep. For this purpose, the contracted specialist company Van Oord uses its Deep Dig-It trencher, an enormous remote-controlled trencher.

The Deep Dig-It is one of the largest and most powerful devices in its class. The trencher weighs 125 tonnes, is more than 17 metres long, well over 8 metres high, and 11 metres wide. With its enormous power it can bury cables deeply even in very hard ground. The trencher is controlled from an offshore installation vessel equipped with a crane to lower and lift out the high-performance machine. The Deep Dig-It moves unmanned over the seabed and creates a deep trench for the cables by liquefying the seabed. Simultaneously, the Deep Dig-It inserts the cables into the trench and seals the seabed afterwards. With work progressing well, Tennet expects the 1,400MW Hollandse Kust (zuid) grid connection to be completed in 2022.

TenneT has started the laying of submarine cables for the Hollandse Kust (zuid) grid connection (picture: Van Oord)

Linkup
> See TenneT press release (html)
> Watch TenneT video of the Deep Dig-It at work (YouTube)

See article on single page

Jacket for Hollandse Kust (zuid) Alpha platform installed

08.09.2020

The offshore wind area Hollandse Kust (zuid) is located 22 kilometres off the coast of the Dutch province of Zuid-Holland. The Dutch-German transmission system operator (TSO) TenneT will connect the wind farms in this area to the onshore substation in the industrial and port area of Maasvlakte via two offshore platforms – Alpha and Beta – and submarine cables. The jacket for the Hollandse Kust (zuid) Alpha platform was transported to the operation site by a heavy-duty vessel on 5 September and successfully installed on the seabed. The Alpha jacket is 29 meters long, 20 meters wide, 46 meters high and weighs 3200 tonnes. It will be further installed in the coming days.

The two 220kv submarine cables will be connected to the jacket over the next few months. In 2021, the platform top side will be placed on the jacket. The Hollandse Kust (zuid) Alpha platform is expected to be operational by the end of 2021. The projects in this new wind area are part of the large-scale offshore expansion programme of TenneT. By the end of 2023, the TSCNET shareholder will have installed 3.5GW of offshore grid connections in the Netherlands, of which the first 1.4GW have already been achieved with Borssele Alpha and Beta. The connection to follow Hollandse Kust (south) will be Hollandse Kust (nord). For all the wind farms in these two areas, TenneT will deploy five identical 700MW transformer platforms and identical 220kV cable connections. “Such standardisation enables TenneT to complete these projects more efficiently, more quickly, and more economically,” explains TenneT COO Tim Meyerjürgens.

The Dutch national roadmap for offshore development provides for an additional 6.1GW of offshore wind farms in the wind energy areas Hollandse Kust (West), Ten Noorden van de Waddeneilanden, and IJmuiden Ver from 2024 to the end of 2030. For the first two areas, TenneT will again use standardised 700MW offshore platforms. The efficient connection of IJmuiden Ver, which is located further out in the North Sea, partly requires other technologies based on DC instead of AC. IJmuiden Ver will have two offshore transformer platforms with a capacity of 2GW each, which is unique in the offshore wind industry.

TenneT has installed the jacket for the Hollandse Kust (zuid) Alpha platform (picture: TenneT)

Linkup
> See TenneT press release (html)

See article on single page