In early 2018, TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO), began preparations for the construction of the new 380kV line in the Rhône Valley between the two substations Chamoson and Chippis, which is to replace the old 220kV line. This new line is of crucial importance for Switzerland’s security of supply, particularly for the transmission of electricity generated in the Valais hydroelectric power plants to the consumption centres in the central Swiss Plateau.

After about 18 months of actual construction, the extra-high voltage line is now taking shape and work is underway along its entire length. But not only do numerous safety measures have to be considered during construction, also the access to some plots of land has not yet been clarified at some pylon sites. These locations are distributed along the entire route of the line. As a decision by the responsible federal authorities is still pending in some cases, Swissgrid has now reviewed the construction plans and postponed commissioning of the new line until summer 2022. As the Federal Evaluation Commission (“Eidgenössische Schätzungskommission”) has given priority to the TSO’s applications, Swissgrid is confident about the further construction of the line.

Swissgrid expects the new 380kV line from Chamoson to Chippis to be commissioned in summer 2022 (picture: Swissgrid)

Linkup
> See Swissgrid news release, in German (html)