Connect+ for data exchange

14.06.2019

The four German transmission system operators (TSOs), the TSCNET shareholders 50Hertz, Amprion, TenneT, and TransnetBW, together with 16 distribution system operators (DSOs) have launched the “Connect+” project to jointly implement the legal requirements of the German Grid Expansion Acceleration Act (Netzausbaubeschleunigungsgesetz – NABEG). The project is a reaction to the increased need for coordination due to the current legislative amendments and intended to facilitate a more transparent exchange of data between grid operators and market participants.

German legislation has specified that, in future, all facilities for the generation or storage of electrical energy with a nominal capacity of 100kW or more must be utilised to prevent foreseeable bottlenecks in the grid. The modified conditions for redispatch apply from 1 October 2021. As the present feed-in management of the grid operators only reacts to acute congestions, an even more intensive cooperation between TSOs and DSOs is required in the future.

The new processes to be developed and introduced within the time frame pose a challenge for all grid operators. In the “Connect+” project, TSOs and DSOs want to develop uniform solutions for data distribution to harmonise data exchange between market participants and operators for congestion management. In a first step, essential specifications such as interfaces and formats are developed and defined.

The four German TSOs and 16 DSOs launch the data exchange project “Connect+” for congestion management

Linkup