From the first submission of the project to the Salzburg state government in September 2012 until the approval of the construction of the second section of the Salzburg Line (“Salzburgleitung”) by the court of last instance, the beautiful Austrian state of Salzburg has certainly seen many sunsets. The Austrian transmission system operator (TSO) APG is now all the more content with the definite legal groundwork for Austria’s most important infrastructure project. Although the legally valid building permit for the Salzburg Line had already been granted by the Austrian Federal Administrative Court in March 2019, there were still final legal details in connection with the project, which the Supreme Administrative Court has now clarified on 20 October 2020, thus confirming the permit.

The new 380kV overhead line will replace the old 220kV line from the 1960s and will be capable of transporting seven times more electricity than the current line. To improve supply security in the city of Salzburg, the first 46-kilometre section of the Salzburg Line from the St. Peter grid node near the German border to the newly constructed Salzburg substation near Elixhausen was already commissioned in January 2011. The second section of the Salzburg Line, from Elixhausen to the Tauern grid node near Kaprun, will now close the western gap in the Austrian “380kV Ring”. This ring-shaped extra-high voltage grid is the backbone of the national electricity supply and crucial for the integration and transmission of renewable energies.

The total length of the new line, which has 449 pylons, is 128 kilometres. However, as old lines will be dismantled when the Salzburg Line is completed and some of them will run jointly on the new line, there will be 229 fewer masts in Salzburg than before. Commissioning of the Salzburg Line is planned for the year 2025, dismantling will be completed by 2026. “With €890m to be invested, the Salzburg Line is by far the most important investment project in the Austrian electricity infrastructure. Of the approx. €350m that APG is investing in the expansion of the electricity grids this year, the Salzburg Line alone has a share of €125m for the domestic economy,” comments Gerhard Christiner, CTO of the Austrian TSCNET shareholder, who also praised the day of the court ruling as a “good day for the energy transition and for the secure supply of electricity in Salzburg and Austria”.

The Austrian Supreme Administrative Court has definitively confirmed the construction permit for the 380kV Salzburg Line of APG (picture: Martin Lugger / APG)

Linkup
> See APG press release, in German (html)