Ernen-Ulrichen 380kV line in operation

21.10.2019

With the erection of the last of a total of 57 pylons, the new extra-high voltage line between the Ernen and Ulrichen substations in the Swiss canton of Valais has now been completed. The 30-kilometre section is part of the 380kV Mörel-Ulrichen line project of TSCNET shareholder Swissgrid, the Swiss transmission system operator (TSO). The line upgrade in the Rhône Valley is vital for the future of Switzerland’s energy supply: In order to fully transfer the hydropower generated in the Valais to the urban areas of Switzerland, the lines of the south-western canton must be connected to the supra-regional 380kV transmission grid, particularly in view of the commissioning of the new Nant de Drance pumped storage power station, scheduled for 2020.

The existing 220kV overhead line between Ernen and Ulrichen is already disconnected. Its 177 pylons will be dismantled from spring 2020 and the former pylon locations will be recultivated. Swissgrid is additionally carrying out nature conservation projects of national importance in the vicinity of the new line. Also starting next year, the Swiss TSO will continue its Valais upgrade project with the new construction of the next section between Ernen and Mörel-Filet, which is expected to be commissioned as 380kV line by the end of 2022.

Swissgrid has commissioned the new 380kV line between Ernen-Ulrichen (picture: Swissgrid)

Linkup
> See Swissgrid news release, in German (html)