Deep Dig-It starts work for Hollandse Kust (zuid) grid

24.09.2020

Hollandse Kust (zuid), an offshore wind area in the Dutch North Sea, is located a good 20 kilometres off the coast of the Dutch province of Zuid-Holland. The Dutch-German transmission system operator (TSO) TenneT is installing the related offshore grid to connect the new offshore wind farms in the area via two offshore platforms and submarine cables to the onshore high-voltage substation that is being built in the Maasvlakte industrial and port area. The jacket for the first of these two offshore platforms has recently been installed and the offshore connection project is now making further progress with the start of the laying of the submarine cables on 22 September.

Four 220kV AC cables with a total length of 42 kilometres each are to be installed in the seabed, of which the first two to the Alpha platform will be laid this year. The other two to the Beta platform will follow in 2021. First, the two cables were brought ashore to the planned Maasvlakte substation via direct drilling. Thereupon the TSCNET shareholder started the marine installation, with the first ten kilometres of the route from the coast at Maasvlakte being extremely challenging. Over this distance, the cables cross the entrance to the port of Rotterdam – Europe’s busiest cargo port – and thus need to be buried more than 5.5 metres deep. For this purpose, the contracted specialist company Van Oord uses its Deep Dig-It trencher, an enormous remote-controlled trencher.

The Deep Dig-It is one of the largest and most powerful devices in its class. The trencher weighs 125 tonnes, is more than 17 metres long, well over 8 metres high, and 11 metres wide. With its enormous power it can bury cables deeply even in very hard ground. The trencher is controlled from an offshore installation vessel equipped with a crane to lower and lift out the high-performance machine. The Deep Dig-It moves unmanned over the seabed and creates a deep trench for the cables by liquefying the seabed. Simultaneously, the Deep Dig-It inserts the cables into the trench and seals the seabed afterwards. With work progressing well, Tennet expects the 1,400MW Hollandse Kust (zuid) grid connection to be completed in 2022.

TenneT has started the laying of submarine cables for the Hollandse Kust (zuid) grid connection (picture: Van Oord)

Linkup
> See TenneT press release (html)
> Watch TenneT video of the Deep Dig-It at work (YouTube)