DA/RE project: Redispatch 2.0

09.04.2020

The grid security initiative DA/RE (“DAta exchange/Redispatch”) was launched in summer 2018 by TransnetBW, the transmission system operator (TSO) from the south-western German state of Baden-Württemberg, and entered the pilot phase on 1 April 2019. The first retrievals of redispatch capacities were carried out in summer 2019 and now the pilot phase of the Baden-Württemberg grid project has been successfully concluded. Apart from TSCNET shareholder TransnetBW, three distribution system operators (DSOs) and four other partners from the fields of virtual power plants, home storage, and energy trading were involved in the DA/RE pilot phase.

Like comparable projects, DA/RE responds to the increasing volatility and decentralisation of electricity generation. In order to stabilise the entire electricity system in the future, DA/RE intends to facilitate the transition from the current redispatch with centralised large-scale power plants to new processes involving the flexibility potential of smaller decentralised generation plants and storage facilities. In the pilot phase, the DA/RE partners have achieved their first project goal: Processes for the coordinated retrieval of redispatch power from the distribution grid over several voltage levels have been developed and successfully tested in practice. The entire process chain from the exchange of planning data via DA/RE internal processes with merit-order based plant selection up to the activation of the physical plant retrieval was tested in three steps. A total of 40 plants of different technologies with rated outputs between 3kW and 30MW were involved.

Key assumptions corroborated
In the pilot phase, the coordinated redispatch retrieval was verified across all voltage levels and the basic functionality of the DA/RE concept was confirmed. With the experience and findings gained from this, the final DA/RE platform is now being developed, for which uniform processes and interfaces to automate the process steps will be defined. This will ensure the scalability and mass suitability of the system and simplify the integration of smaller grid and plant operators.

The two DA/RE project managers, Florian Gutekunst from TransnetBW and Kilian Geschermann from the DSO Netze BW, describe DA/RE as an open project: “We are looking forward to involving further interested parties from the ranks of grid and plant operators as fellow campaigners. We are all facing growing challenges due to the transformation of the generation landscape; together we can find smart solutions and better meet the challenges.”

The pilot phase of the DA/RE project for smart decentralised redispatch solutions has successfully been concluded

Linkup
> See TransnetBW press release, in German (html)
> Visit DA/RE website, in German (html)