Construction of ULTRANET substation approved

27.03.2020

The Philippsburg nuclear power plant in the German state of Baden-Württemberg was shut down completely on 31 December 2019. On the power plant site, TSCNET shareholder TransnetBW, the Transmission System Operator (TSO) from the southwest of Germany, is planning a new DC substation with a required area of around 100,000m². The substation is to become one of the most important energy hubs in Germany’s future energy landscape, as the supra-regional high-voltage direct current (HVDC) line ULTRANET will be connected here to the regional 380kV AC grid.

After intensive planning, TransnetBW submitted the application for construction permit to the competent district administration for examination in June 2018. The Landratsamt Karlsruhe has now approved the plans of the TSO. “The DC substation plays a central role in integrating renewable energies into the transmission grid,” explains Dr. Werner Götz, Chairman of the TransnetBW Executive Board. “In the future, renewable electricity will flow from the Philippsburg site to the entire region. We are thus laying a cornerstone for supply security in a future without nuclear power and coal.”

ULTRANET, a European Project of Common Interest (PCI), is jointly implemented by TransnetBW and the further TSCNET shareholder Amprion. It will transfer wind energy generated in the northwest of Germany to the industrially highly developed southwest. The Philippsburg substation represents the southern end point of ULTRANET. Here, the DC transmitted via ULTRANET to Philippsburg is converted into AC and distributed throughout the region. Vice-versa, the substation allows the conversion of AC into DC, e.g. to transport surplus photovoltaic power from the south to the north.

TransnetBW has received official approval for the construction of the ULTRANET substation in Philippsburg (architectural sketch of the substation: Codema International GmbH / TransnetBW)

Linkup
> See TransnetBW press release, in German (html)