COBRAcable market launch on 7 September

02.09.2019

After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule. The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO.

The high-voltage DC cable with a length of about 325km has a capacity of 700MW. The Netherlands can import more sustainable electricity from Denmark through COBRAcable, mainly wind energy. In addition, the cable provides Dutch capacity on a structural basis for the Danish electricity grid, thus ensuring security of supply in Denmark, which of course also works the other way round. Moreover, the cable connection is designed in such a way that an offshore wind farm can be connected at a later date, so that COBRAcable contributes to a sustainable European energy landscape.

The COBRAcable interconnector of Energinet and Tennet is available to the market from 7 September (picture: screenshot taken from TenneT-video “First pile COBRAcable”, YouTube)

Linkup
> See TenneT press release (html)